Outage planning results

Last updated: Fri, 22/02/2019 - 12:10
Your current search

Sites: all sites selected

Outages search found 3006 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
OTA PEN 6 NNI G 01/04/2019 - 07:00 06/04/2019 - 18:30 C RS 1076584 Approved 07/05/2012 - 15:49
OTA ROS 1 NNI G 06/11/2018 - 18:00 31/07/2019 - 18:00 C OPE 1072983 Released 07/05/2012 - 15:49
OTA ROS 1 NNI G 23/04/2019 - 07:30 24/04/2019 - 19:00 C RS 1071688 Approved 07/05/2012 - 15:49
OTA ROS 2 NNI G 25/04/2019 - 07:30 26/04/2019 - 19:00 C RS 1071689 Approved 07/05/2012 - 15:49
OTA ROS 2 NNI G 01/04/2019 - 07:00 02/04/2019 - 18:00 C OPE 1077255 Approved 07/05/2012 - 15:49
OTA SWN 1 NNI G 25/03/2019 - 07:30 26/03/2019 - 18:30 C RS 1074206 Approved 07/05/2012 - 15:49
OTA T2 NNI G 01/05/2019 - 07:00 01/05/2019 - 17:00 D OPE 1077187 Approved 07/05/2012 - 15:49
OTA T2 NNI G 04/05/2019 - 07:00 04/05/2019 - 17:00 D RS 1076834 Approved 07/05/2012 - 15:49
OTA T2 NNI G 05/03/2019 - 07:30 12/03/2019 - 18:30 C RS 1069957 Cancelled 07/05/2012 - 15:49
OTA T4 NNI G 16/10/2019 - 07:00 19/05/2020 - 18:00 C RS 1069034 Approved 07/05/2012 - 15:49
OTA T4 NNI G 01/05/2019 - 07:00 01/05/2019 - 17:00 D RS 1075793 Approved 07/05/2012 - 15:49
OTA T4 NNI G 03/10/2019 - 07:30 04/10/2019 - 18:30 D RS 1070145 Cancelled 07/05/2012 - 15:49
OTA WKM 1 NNI G 04/05/2019 - 07:00 04/05/2019 - 17:00 D RS 1076843 Approved 07/05/2012 - 15:49
OTA WKM 1 NNI G 08/04/2019 - 07:30 10/04/2019 - 18:30 C RS 1066133 Approved 07/05/2012 - 15:49
OTA WKM 2 NNI G 11/03/2019 - 07:30 16/03/2019 - 18:30 C RS 1066137 Approved 07/05/2012 - 15:49
OTA WKM 2 NNI G 11/04/2019 - 07:30 16/04/2019 - 18:30 C RS 1066136 Approved 07/05/2012 - 15:49
OWH T1 NNI G 30/04/2019 - 07:30 30/04/2019 - 17:00 D RS 1073853 Approved 07/05/2012 - 15:49
OWH T2 NNI G 22/03/2019 - 07:30 22/03/2019 - 18:30 D RS 1075931 Approved 07/05/2012 - 15:49
PEN T10 NNI G 21/03/2019 - 07:00 22/03/2019 - 18:00 C RS 1064349 Approved 07/05/2012 - 15:49
PEN T10 NNI G 29/04/2019 - 07:00 05/05/2019 - 17:30 C OPE 1075171 Approved 07/05/2012 - 15:49
PEN T10 NNI G 08/05/2019 - 16:00 11/05/2019 - 18:30 C OPE 1077261 Approved 07/05/2012 - 15:49
PEN T10 NNI G 13/05/2019 - 07:00 18/05/2019 - 18:30 C OPE 1077274 Approved 07/05/2012 - 15:49
PEN T10 NNI G 20/05/2019 - 07:00 25/05/2019 - 18:30 C OPE 1077277 Approved 07/05/2012 - 15:49
PEN T10 NNI G 27/05/2019 - 07:00 01/06/2019 - 18:30 C OPE 1077283 Approved 07/05/2012 - 15:49
OTA PEN 6 NNI G 29/04/2019 - 07:00 04/05/2019 - 18:30 C RS 1076585 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.