Outage planning results

Last updated: Sat, 17/04/2021 - 22:40
Your current search

Sites: all sites selected

Outages search found 2116 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
TMU T2 NNI G 28/04/2021 - 07:00 30/04/2021 - 19:00 C RS 1090883 Approved 07/05/2012 - 15:49
TMU T2 NNI G 07/05/2021 - 07:30 07/05/2021 - 11:30 D RS 1103081 Approved 07/05/2012 - 15:49
HAM PAO WHU 2 NNI G 17/05/2021 - 07:30 21/05/2021 - 19:00 C RS 1088603 Approved 07/05/2012 - 15:49
WEL T1 NNI G 20/04/2021 - 07:30 20/04/2021 - 18:00 D RS 1085919 Approved 07/05/2012 - 15:49
WEL T1 NNI G 19/06/2021 - 06:00 22/06/2021 - 18:00 C RS 1097946 Approved 07/05/2012 - 15:49
WEL T1 NNI G 24/05/2021 - 06:00 28/05/2021 - 17:59 C RS 1097939 Approved 07/05/2012 - 15:49
WHU T3 NNI G 22/06/2021 - 07:30 23/06/2021 - 18:30 C RS 1103277 Approved 07/05/2012 - 15:49
WIR T1 NNI G 19/04/2021 - 07:30 19/04/2021 - 18:00 D RS 1103545 Approved 07/05/2012 - 15:49
WIR T1 NNI G 12/03/2022 - 07:30 15/03/2022 - 18:30 C RS 1079534 Approved 07/05/2012 - 15:49
WIR T1 NNI G 13/09/2021 - 07:30 27/09/2021 - 18:30 C RS 1079533 Approved 07/05/2012 - 15:49
WIR T2 NNI G 21/03/2022 - 07:30 24/03/2022 - 18:30 C RS 1079539 Approved 07/05/2012 - 15:49
WIR T2 NNI G 04/10/2021 - 07:30 20/10/2021 - 18:30 C RS 1079538 Approved 07/05/2012 - 15:49
WIR T2 NNI G 27/04/2021 - 07:30 28/04/2021 - 18:00 C RS 1103547 Approved 07/05/2012 - 15:49
ARI CB 48 NNI G 18/10/2021 - 08:00 20/10/2021 - 18:00 C CLO 1078228 Cancelled 07/05/2012 - 15:49
ARI CB 48 NNI G 25/10/2021 - 08:00 27/10/2021 - 18:00 C CLO 1078232 Cancelled 07/05/2012 - 15:49
ARI CB 48 NNI G 29/11/2021 - 08:00 03/12/2021 - 18:00 C CLO 1078241 Cancelled 07/05/2012 - 15:49
ARI CB 48 NNI G 06/12/2021 - 08:00 10/12/2021 - 18:00 C CLO 1078245 Cancelled 07/05/2012 - 15:49
ARI CB 48 NNI G 27/04/2021 - 07:30 28/04/2021 - 18:00 D CLO 1103137 Approved 07/05/2012 - 15:49
HIN T1 NNI G 03/06/2021 - 08:00 03/06/2021 - 16:00 D RS 1099891 Approved 07/05/2012 - 15:49
HIN T1 NNI G 20/05/2021 - 07:00 20/05/2021 - 18:30 D RS 1101969 Approved 07/05/2012 - 15:49
ALB CB 658 NNI G 06/04/2021 - 07:30 23/04/2021 - 18:00 C RS 1103391 Released 07/05/2012 - 15:49
MTO T1 NNI G 10/05/2021 - 07:30 14/05/2021 - 18:30 C RS 1097935 Approved 07/05/2012 - 15:49
MTO T1 NNI G 15/06/2021 - 06:00 18/06/2021 - 18:30 C RS 1097942 Approved 07/05/2012 - 15:49
MTO T2 NNI G 19/06/2021 - 06:00 22/06/2021 - 18:00 C RS 1097945 Approved 07/05/2012 - 15:49
TGA RTU 1 NNI G 27/04/2021 - 08:00 28/04/2021 - 18:00 D RS 1098085 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.