Outage planning results

Last updated: Fri, 07/05/2021 - 12:40
Your current search

Sites: all sites selected

Outages search found 3559 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
CCT 2087 BPE MHO SNI G 15/06/2021 - 09:30 15/06/2021 - 16:30 D RS 1102778 Approved 15/08/2019 - 15:00
ROT T2 NNI G 10/08/2021 - 07:30 13/08/2021 - 18:30 D RS 1100195 Approved 07/05/2012 - 15:49
ROT T2 NNI G 18/10/2021 - 07:30 22/10/2021 - 18:30 C RS 1085851 Approved 07/05/2012 - 15:49
ROT T3 NNI G 18/10/2021 - 07:30 22/10/2021 - 18:30 C RS 1085852 Approved 07/05/2012 - 15:49
ROT T4 NNI G 01/09/2021 - 07:30 02/09/2021 - 18:30 D RS 1100257 Approved 07/05/2012 - 15:49
ROT T5 NNI G 01/09/2021 - 07:30 02/09/2021 - 18:30 D RS 1100256 Approved 07/05/2012 - 15:49
ROT TRK 1 NNI G 01/09/2021 - 07:30 02/09/2021 - 18:30 D RS 1100255 Approved 07/05/2012 - 15:49
ROT TRK 2 NNI G 16/08/2021 - 07:30 18/08/2021 - 16:30 D RS 1100216 Approved 07/05/2012 - 15:49
ROT TRK 2 NNI G 18/10/2021 - 07:30 22/10/2021 - 18:30 C RS 1085856 Approved 07/05/2012 - 15:49
ROT WHE 1 NNI G 18/10/2021 - 07:30 22/10/2021 - 18:30 C RS 1092958 Approved 07/05/2012 - 15:49
TAK T5 NNI G 01/11/2021 - 07:30 06/11/2021 - 18:30 C RS 1085159 Approved 07/05/2012 - 15:49
TAK T5 NNI G 06/12/2021 - 07:30 11/12/2021 - 18:30 C RS 1085161 Approved 07/05/2012 - 15:49
TAK T5 NNI G 02/08/2021 - 08:00 07/08/2021 - 18:30 D RS 1100151 Approved 07/05/2012 - 15:49
TAK T5 NNI G 04/10/2021 - 07:30 09/10/2021 - 18:30 C RS 1085157 Approved 07/05/2012 - 15:49
TAK T5 NNI G 28/05/2021 - 07:30 28/05/2021 - 18:30 D RS 1098143 Approved 07/05/2012 - 15:49
TAK T8 NNI G 11/10/2021 - 07:30 16/10/2021 - 18:30 C RS 1085163 Approved 07/05/2012 - 15:49
TAK T8 NNI G 23/08/2021 - 08:00 28/08/2021 - 18:30 D RS 1100235 Approved 07/05/2012 - 15:49
TAK T8 NNI G 13/12/2021 - 07:30 18/12/2021 - 18:30 C RS 1085167 Approved 07/05/2012 - 15:49
TAK T8 NNI G 08/11/2021 - 07:30 13/11/2021 - 18:30 C RS 1085165 Approved 07/05/2012 - 15:49
TAK T8 NNI G 02/11/2022 - 08:00 02/11/2022 - 16:00 D RS 1097042 Approved 07/05/2012 - 15:49
TAK T8 NNI G 07/03/2022 - 08:00 10/03/2022 - 18:30 C RS 1097039 Approved 07/05/2012 - 15:49
TAK T8 NNI G 09/02/2022 - 07:30 18/02/2022 - 18:30 C RS 1097036 Approved 07/05/2012 - 15:49
TAK T8 NNI G 23/03/2022 - 07:00 25/03/2022 - 18:00 D RS 1101202 Approved 07/05/2012 - 15:49
TGA T2 NNI G 17/08/2021 - 07:30 17/08/2021 - 18:30 D RS 1100226 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 27/07/2021 - 08:00 29/07/2021 - 18:30 D RS 1097653 Cancelled 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.