Outage planning results

Last updated: Wed, 16/10/2019 - 16:40
Your current search

Sites: all sites selected

Outages search found 4067 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
DOB T11 SI G 20/01/2020 - 07:30 24/01/2020 - 18:30 C RS 1072788 Approved 07/05/2012 - 15:52
DOB T11 SI G 27/01/2020 - 07:30 05/02/2020 - 18:30 C RS 1072786 Approved 07/05/2012 - 15:52
DOB T11 RFN IGH 2 SI G 27/01/2020 - 07:30 05/02/2020 - 18:30 C RS 1069975 Cancelled 07/05/2012 - 15:52
DOB T11 RFN IGH 2 SI G 20/01/2020 - 07:30 24/01/2020 - 18:30 C RS 1069182 Cancelled 07/05/2012 - 15:52
OTA 220BS CHANGE NNI G 31/10/2019 - 07:00 31/10/2019 - 07:30 D PSO 1084281 Approved 07/05/2012 - 15:49
OTA 220BS CHANGE NNI G 31/10/2019 - 18:00 31/10/2019 - 19:00 D PSO 1084282 Approved 07/05/2012 - 15:49
CCT 8566 BLN HAR SI G 10/12/2019 - 07:30 10/12/2019 - 19:00 D RS 1081141 Approved 07/05/2012 - 15:52
ABY T2 SI G 07/11/2019 - 23:00 08/11/2019 - 05:00 C RS 1069101 Approved 07/05/2012 - 15:51
ABY TIM 1 SI G 09/12/2019 - 07:30 13/12/2019 - 18:30 C RS 1069102 Approved 07/05/2012 - 15:51
ABY TKA 1 SI G 02/12/2019 - 07:30 06/12/2019 - 18:30 C RS 1069465 Approved 07/05/2012 - 15:51
HKK KUM 1 SI G 17/12/2019 - 06:30 19/12/2019 - 18:30 C RS 1069979 Approved 07/05/2012 - 15:51
HKK KUM 1 SI G 20/12/2019 - 06:30 20/12/2019 - 18:30 D RS 1069981 Cancelled 07/05/2012 - 15:51
HKK KUM 1 SI G 16/06/2020 - 07:30 16/06/2020 - 18:30 D RS 1074014 Approved 07/05/2012 - 15:51
HKK KUM 1 SI G 22/06/2020 - 07:30 22/06/2020 - 18:30 D RS 1074007 Approved 07/05/2012 - 15:51
HKK OTI 2 SI G 17/12/2019 - 06:30 19/12/2019 - 18:30 C RS 1069190 Cancelled 07/05/2012 - 15:51
HKK OTI 2 SI G 12/05/2020 - 06:30 14/05/2020 - 18:30 C RS 1083762 Approved 07/05/2012 - 15:51
HKK OTI 2 SI G 09/12/2019 - 06:30 16/12/2019 - 18:30 C RS 1070009 Approved 07/05/2012 - 15:51
APS 66BS SI G 03/12/2019 - 09:00 05/12/2019 - 16:00 C RS 1082135 Approved 07/05/2012 - 15:51
APS CLH 1 SI G 03/12/2019 - 09:00 05/12/2019 - 16:00 C RS 1082112 Approved 07/05/2012 - 15:51
APS CLH 1 SI G 17/02/2020 - 05:30 21/02/2020 - 18:30 C RS 1069823 Approved 07/05/2012 - 15:51
APS CLH 1 SI G 16/03/2020 - 05:30 20/03/2020 - 18:30 C RS 1069898 Approved 07/05/2012 - 15:51
APS OTI 1 SI G 02/03/2020 - 05:30 06/03/2020 - 18:30 C RS 1069827 Approved 07/05/2012 - 15:51
APS OTI 1 SI G 03/12/2019 - 09:00 05/12/2019 - 16:00 C RS 1082111 Approved 07/05/2012 - 15:51
APS T1 SI G 20/11/2019 - 08:00 05/12/2019 - 16:00 C RS 1082107 Approved 07/05/2012 - 15:51
BDE GOR 1 SI G 02/04/2020 - 07:30 03/04/2020 - 18:30 C RS 1077048 Approved 07/05/2012 - 15:51
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.