Outage planning results

Last updated: Thu, 18/08/2022 - 10:40
Your current search

Sites: all sites selected

Outages search found 3207 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
PEN FDR 1682 NNI L 21/01/2023 - 07:30 22/01/2023 - 18:30 D RS 1113237 Approved 07/05/2012 - 15:49
PEN FDR 1692 NNI L 21/01/2023 - 07:30 22/01/2023 - 18:30 D RS 1113238 Approved 07/05/2012 - 15:49
PEN FDR 1702 NNI L 21/01/2023 - 07:30 22/01/2023 - 18:30 D RS 1113239 Approved 07/05/2012 - 15:49
PEN FDR 1712 NNI L 21/01/2023 - 07:30 22/01/2023 - 18:30 D RS 1113240 Approved 07/05/2012 - 15:49
WEL T1 NNI G 20/02/2023 - 07:30 24/02/2023 - 07:30 C RS 1113324 Cancelled 07/05/2012 - 15:49
TGA T1 NNI G 06/03/2023 - 07:30 07/03/2023 - 18:30 C RS 1113349 Approved 07/05/2012 - 15:49
TMU 11BZ A2 NNI L 29/11/2022 - 08:00 02/12/2022 - 18:00 D RS 1111495 Approved 07/05/2012 - 15:49
TMU 11BZ A2 NNI L 21/02/2023 - 08:00 24/02/2023 - 18:00 D RS 1116336 Approved 07/05/2012 - 15:49
PEN RTU 1 NNI G 09/11/2022 - 08:00 09/11/2022 - 18:00 D RS 1117167 Approved 07/05/2012 - 15:49
TMU 11BZ A1 NNI L 21/02/2023 - 08:00 24/02/2023 - 18:00 D RS 1111472 Approved 07/05/2012 - 15:49
TMU 11BZ A1 NNI L 29/11/2022 - 08:00 02/12/2022 - 18:00 D RS 1116334 Approved 07/05/2012 - 15:49
PEN RTU 1 NNI G 02/11/2022 - 08:00 02/11/2022 - 18:00 D RS 1117165 Approved 07/05/2012 - 15:49
WEL T1 NNI G 13/03/2023 - 07:00 19/03/2023 - 18:30 C RS 1103169 Approved 07/05/2012 - 15:49
SWN 220BZ NNI G 21/06/2023 - 07:30 22/06/2023 - 18:30 D RS 1113185 Approved 07/05/2012 - 15:49
KAW 11BZ B NNI L 14/06/2023 - 10:00 14/06/2023 - 12:00 D RS 1096683 Approved 07/05/2012 - 15:49
PEN RTU 1 NNI G 16/11/2022 - 08:00 16/11/2022 - 18:00 D RS 1117169 Approved 07/05/2012 - 15:49
KAW 11BZ B NNI L 12/06/2023 - 10:00 12/06/2023 - 12:00 D RS 1096680 Approved 07/05/2012 - 15:49
KAW 11BZ A NNI L 12/06/2023 - 08:00 12/06/2023 - 10:00 D RS 1096679 Approved 07/05/2012 - 15:49
PEN RTU 1 NNI G 19/10/2022 - 08:00 19/10/2022 - 18:00 D RS 1117163 Approved 07/05/2012 - 15:49
WEL T1 NNI G 20/02/2023 - 07:00 24/02/2023 - 18:30 C RS 1103166 Approved 07/05/2012 - 15:49
TAK T8 NNI G 02/11/2022 - 08:00 02/11/2022 - 16:00 D RS 1097042 Cancelled 07/05/2012 - 15:49
ROT T3 NNI G 17/04/2023 - 08:00 19/04/2023 - 18:30 C RS 1113450 Approved 07/05/2012 - 15:49
KAW 11BZ A NNI L 14/06/2023 - 08:00 14/06/2023 - 10:00 D RS 1096682 Approved 07/05/2012 - 15:49
HLY 220BZ B NNI G 01/09/2022 - 08:30 02/09/2022 - 16:00 D RS 1110862 Approved 07/05/2012 - 15:49
PEN RTU 1 NNI G 05/10/2022 - 08:00 05/10/2022 - 18:00 D RS 1117158 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.