Outage planning results

Last updated: Thu, 26/05/2022 - 16:40
Your current search

Sites: all sites selected

Outages search found 3509 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BPE LTN 2 SNI G 12/12/2022 - 07:30 12/12/2022 - 18:30 D RS 1112364 Approved 01/09/2020 - 13:18
BPE LTN 2 SNI G 14/12/2022 - 07:30 14/12/2022 - 18:30 D RS 1112365 Approved 01/09/2020 - 13:18
BPE LTN 2 SNI G 06/03/2023 - 07:30 10/03/2023 - 18:30 C RS 1112366 Approved 01/09/2020 - 13:18
HAY WIL LTN 1 SNI G 20/02/2023 - 07:00 26/02/2023 - 18:30 C RS 1112647 Approved 06/04/2021 - 14:24
HAY WIL LTN 1 SNI G 16/01/2023 - 07:30 20/01/2023 - 18:30 C RS 1112568 Approved 06/04/2021 - 14:24
HAY WIL LTN 1 SNI G 30/01/2023 - 07:30 03/02/2023 - 18:30 C RS 1112594 Approved 06/04/2021 - 14:24
HAY WIL LTN 1 SNI G 24/01/2023 - 07:30 27/01/2023 - 18:30 C RS 1112581 Approved 06/04/2021 - 14:24
HAY WIL LTN 1 SNI G 07/02/2023 - 07:30 10/02/2023 - 18:30 C RS 1112604 Approved 06/04/2021 - 14:24
HAY WIL LTN 2 SNI G 18/01/2023 - 06:00 18/01/2023 - 18:30 D RS 1112639 Approved 06/04/2021 - 14:30
HAY WIL LTN 2 SNI G 01/06/2022 - 07:30 02/06/2022 - 17:30 C RS 1112187 Approved 06/04/2021 - 14:30
HAY WIL LTN 2 SNI G 27/02/2023 - 07:30 03/03/2023 - 18:30 C RS 1112670 Approved 06/04/2021 - 14:30
HAY WIL LTN 2 SNI G 06/03/2023 - 07:30 10/03/2023 - 18:30 C RS 1112715 Approved 06/04/2021 - 14:30
HAY WIL LTN 2 SNI G 13/03/2023 - 07:30 17/03/2023 - 18:30 C RS 1112722 Approved 06/04/2021 - 14:30
HAY WIL LTN 2 SNI G 06/04/2023 - 07:30 06/04/2023 - 18:30 D RS 1112796 Approved 06/04/2021 - 14:30
TWZ RTU 1 SI G 19/10/2022 - 10:05 19/10/2022 - 13:00 D SCA 1116312 Approved 07/05/2012 - 15:51
TWZ RTU 1 SI G 20/07/2022 - 13:05 20/07/2022 - 16:00 D SCA 1107532 Approved 07/05/2012 - 15:51
TWZ RTU 1 SI G 31/05/2022 - 13:05 31/05/2022 - 16:05 D SCA 1116309 Approved 07/05/2012 - 15:51
BOB RTU 2 NNI G 21/11/2022 - 09:00 21/11/2022 - 15:00 D SCA 1115829 Approved 07/05/2012 - 15:50
BOB RTU 2 NNI G 30/08/2022 - 08:30 30/08/2022 - 16:00 D SCA 1115977 Approved 07/05/2012 - 15:50
BOB RTU 1 NNI G 16/08/2022 - 08:30 16/08/2022 - 16:00 D SCA 1110871 Approved 07/05/2012 - 15:49
BOB RTU 2 NNI G 04/10/2022 - 08:30 04/10/2022 - 16:00 D SCA 1115979 Approved 07/05/2012 - 15:50
WIR RTU 1 NNI G 28/09/2022 - 09:00 28/09/2022 - 15:00 D SCA 1104600 Approved 07/05/2012 - 15:49
TWZ RTU 1 SI G 28/09/2022 - 12:30 28/09/2022 - 16:00 D SCA 1106784 Approved 07/05/2012 - 15:51
BEN RTU 1 SI G 19/10/2022 - 08:00 19/10/2022 - 10:00 D SCA 1116311 Approved 07/05/2012 - 15:51
BOB RTU 1 NNI G 30/08/2022 - 08:30 30/08/2022 - 16:00 D SCA 1110876 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.