Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
STK FDR 92 SI G 14/09/2020 - 08:00 18/09/2020 - 17:00 C RS 1094681 Approved 07/05/2012 - 15:51
STK FDR 92 SI G 09/11/2020 - 07:30 10/11/2020 - 18:30 D RS 1087367 Approved 07/05/2012 - 15:51
STK FDR 102 SI G 02/11/2020 - 07:30 03/11/2020 - 18:30 C RS 1087358 Approved 07/05/2012 - 15:51
STK FDR 102 SI G 03/08/2020 - 08:00 07/08/2020 - 17:00 C RS 1094680 Approved 07/05/2012 - 15:51
NMA 1097 1136 SI L 27/10/2020 - 08:00 29/10/2020 - 18:30 C RS 1087252 Approved 07/05/2012 - 15:51
NMA 1127 1096 SI L 03/11/2020 - 07:30 04/11/2020 - 18:30 C RS 1087253 Approved 07/05/2012 - 15:51
NMA 220BS A1 SI G 07/12/2020 - 07:30 07/12/2020 - 18:30 D RS 1087255 Approved 07/05/2012 - 15:51
NMA 220BS A3 SI G 09/12/2020 - 07:30 10/12/2020 - 18:30 D RS 1087256 Approved 07/05/2012 - 15:51
NMA 220BS A4 SI G 30/03/2021 - 07:30 30/03/2021 - 18:30 D RS 1087264 Approved 07/05/2012 - 15:51
NMA 220BS B SI G 31/03/2021 - 07:30 31/03/2021 - 18:30 D RS 1087265 Approved 07/05/2012 - 15:51
NMA 687 835 SI G 11/12/2020 - 07:30 11/12/2020 - 18:30 D RS 1087257 Approved 07/05/2012 - 15:51
NMA C 3 SI G 11/12/2020 - 07:30 11/12/2020 - 18:30 D RS 1087258 Approved 07/05/2012 - 15:51
NMA CB 718 SI G 12/12/2020 - 07:30 12/12/2020 - 18:30 D RS 1087259 Approved 07/05/2012 - 15:51
NMA CB 738 SI G 13/12/2020 - 07:30 13/12/2020 - 18:30 D RS 1087260 Approved 07/05/2012 - 15:51
NMA T1 SI G 03/11/2020 - 07:30 04/11/2020 - 18:30 C RS 1087254 Approved 07/05/2012 - 15:51
NMA T2 SI G 27/10/2020 - 08:00 29/10/2020 - 18:30 C RS 1087262 Approved 07/05/2012 - 15:51
NMA TWI 1 SI G 29/03/2021 - 07:30 02/04/2021 - 18:30 C RS 1087263 Approved 07/05/2012 - 15:51
NMA TWI 1 SI G 24/05/2021 - 07:30 28/05/2021 - 18:30 C RS 1082831 Approved 07/05/2012 - 15:51
NMA TWI 2 SI G 07/06/2021 - 07:30 12/06/2021 - 18:30 C RS 1082832 Approved 07/05/2012 - 15:51
NMA TWI 2 SI G 06/08/2020 - 07:30 07/08/2020 - 18:30 C RS 1087808 Approved 07/05/2012 - 15:51
OAM STU BPD WTK 2 SI G 17/05/2021 - 07:30 21/05/2021 - 18:30 C RS 1089248 Approved 07/05/2012 - 15:51
OAM BPT WTK 1 SI G 24/05/2021 - 07:30 28/05/2021 - 18:30 C RS 1089247 Approved 07/05/2012 - 15:51
OHB 806 1007 SI G 03/03/2021 - 07:30 03/03/2021 - 18:30 D RS 1087268 Approved 07/05/2012 - 15:51
OHB TWZ 3 SI G 02/03/2021 - 07:30 02/03/2021 - 18:30 D RS 1087271 Approved 07/05/2012 - 15:51
OHB TWZ 3 SI G 10/09/2020 - 07:30 10/09/2020 - 18:30 D RS 1087797 Approved 07/05/2012 - 15:51
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.