Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
TAK T5 NNI G 04/10/2021 - 07:30 09/10/2021 - 18:30 C RS 1085157 Approved 07/05/2012 - 15:49
TAK T8 NNI G 11/10/2021 - 07:30 16/10/2021 - 18:30 C RS 1085163 Approved 07/05/2012 - 15:49
TAK T8 NNI G 08/11/2021 - 07:30 13/11/2021 - 18:30 C RS 1085165 Approved 07/05/2012 - 15:49
TAK T8 NNI G 13/12/2021 - 07:30 18/12/2021 - 18:30 C RS 1085167 Approved 07/05/2012 - 15:49
TAK T8 NNI G 07/03/2022 - 08:00 10/03/2022 - 18:30 C RS 1097039 Approved 07/05/2012 - 15:49
TAK T8 NNI G 09/02/2022 - 07:30 18/02/2022 - 18:30 C RS 1097036 Approved 07/05/2012 - 15:49
KAW T2 NNI G 18/05/2021 - 07:30 18/05/2021 - 18:30 D RS 1099885 Approved 07/05/2012 - 15:49
TGA T1 NNI G 06/05/2021 - 07:30 06/05/2021 - 18:30 D RS 1094093 Approved 07/05/2012 - 15:49
TGA T3 NNI G 03/05/2021 - 08:00 05/05/2021 - 18:00 C RS 1098234 Approved 07/05/2012 - 15:49
KAW T14 NNI G 14/06/2023 - 07:00 15/06/2023 - 18:00 C RS 1096681 Approved 07/05/2012 - 15:49
TGA T3 NNI G 19/04/2021 - 08:00 24/04/2021 - 16:00 C RS 1099904 Released 07/05/2012 - 15:49
TMI T1 NNI G 19/04/2021 - 13:00 23/04/2021 - 11:30 C RS 1097925 Released 07/05/2012 - 15:49
TMU FDR 23 NNI L 01/06/2021 - 07:30 04/06/2021 - 18:00 D RS 1085896 Approved 07/05/2012 - 15:49
TMU T2 NNI G 06/07/2021 - 07:30 06/07/2021 - 12:30 D RS 1103081 Approved 07/05/2012 - 15:49
ARI KIN 2 NNI G 01/06/2021 - 07:30 01/06/2021 - 19:00 D RS 1085403 Approved 07/05/2012 - 15:49
TMU T2 NNI G 28/06/2021 - 07:00 30/06/2021 - 19:00 C RS 1090883 Approved 07/05/2012 - 15:49
TMU T2 NNI G 02/07/2021 - 10:00 02/07/2021 - 18:00 D RS 1103794 Approved 07/05/2012 - 15:49
WEL T1 NNI G 19/06/2021 - 06:00 22/06/2021 - 18:00 C RS 1097946 Approved 07/05/2012 - 15:49
WEL T1 NNI G 24/05/2021 - 06:00 28/05/2021 - 17:59 C RS 1097939 Approved 07/05/2012 - 15:49
WHU T3 NNI G 22/06/2021 - 07:30 23/06/2021 - 18:30 C RS 1103277 Approved 07/05/2012 - 15:49
WIR FDR 2152 NNI L 06/05/2021 - 07:30 06/05/2021 - 16:00 D RS 1104125 Approved 07/05/2012 - 15:49
WIR T1 NNI G 25/06/2021 - 08:00 25/06/2021 - 12:00 D RS 1103786 Approved 07/05/2012 - 15:49
WIR T1 NNI G 21/06/2021 - 08:00 21/06/2021 - 11:59 D RS 1103782 Approved 07/05/2012 - 15:49
KAW T12 NNI G 02/11/2021 - 07:30 05/11/2021 - 18:00 C RS 1085609 Approved 07/05/2012 - 15:49
KAW T11 NNI G 02/11/2021 - 07:30 04/11/2021 - 18:00 C RS 1085608 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.