Outage planning results

Last updated: Fri, 18/09/2020 - 19:40
Your current search

Sites: all sites selected

Outages search found 4079 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
KMO TRK 1 NNI G 30/11/2020 - 07:30 01/12/2020 - 18:00 D RS 1085657 Cancelled 07/05/2012 - 15:50
KMO TRK 1 NNI G 12/01/2021 - 07:30 13/01/2021 - 18:00 C RS 1088039 Approved 07/05/2012 - 15:50
KMO TRK 2 NNI G 07/12/2020 - 07:30 11/12/2020 - 18:00 C RS 1085658 Approved 07/05/2012 - 15:50
KMO MTM TGA 2 NNI G 18/01/2021 - 07:30 18/01/2021 - 18:00 D RS 1085651 Approved 07/05/2012 - 15:50
KMO MTM 1 NNI G 12/11/2020 - 07:30 12/11/2020 - 18:30 D RS 1093469 Approved 07/05/2012 - 15:50
KMO TMI 1 NNI G 25/01/2021 - 07:30 29/01/2021 - 18:00 C RS 1096382 Approved 07/05/2012 - 15:50
KMO TMI 1 NNI G 04/02/2021 - 07:30 05/02/2021 - 17:30 C RS 1095102 Approved 07/05/2012 - 15:50
KMO TMI 1 NNI G 17/02/2021 - 07:30 18/02/2021 - 18:00 C RS 1085656 Approved 07/05/2012 - 15:50
KAW MAT 1 PROT1 NNI G 02/12/2020 - 15:30 02/12/2020 - 18:00 D RS 1095241 Approved 07/05/2012 - 15:50
KAW MAT 2 PROT1 NNI G 02/12/2020 - 12:30 02/12/2020 - 15:00 D RS 1095242 Approved 07/05/2012 - 15:50
BOB C 11 NNI G 01/10/2020 - 07:00 02/10/2020 - 18:00 C RS 1094395 Approved 07/05/2012 - 15:50
BOB 110CBF NNI G 24/09/2020 - 07:00 25/09/2020 - 18:00 C RS 1094392 Approved 07/05/2012 - 15:50
HEP C 13 NNI G 21/09/2020 - 08:30 21/09/2020 - 17:00 D RS 1091336 Approved 07/05/2012 - 15:50
HLY OHW 1 NNI G 30/11/2020 - 07:30 02/12/2020 - 18:30 C RS 1096342 Approved 07/05/2012 - 15:50
HLY OHW 1 NNI G 03/02/2021 - 07:30 05/02/2021 - 18:30 C RS 1096453 Approved 07/05/2012 - 15:50
HAM OHW 1 NNI G 28/11/2020 - 07:00 28/11/2020 - 18:00 D RS 1083932 Approved 07/05/2012 - 15:50
HAM OHW 1 NNI G 27/02/2021 - 07:30 28/02/2021 - 18:00 D RS 1085526 Approved 07/05/2012 - 15:50
HAM OHW 1 NNI G 06/03/2021 - 07:00 07/03/2021 - 19:00 D RS 1085527 Approved 07/05/2012 - 15:50
PEN RTU 2 NNI G 23/09/2020 - 09:00 23/09/2020 - 14:00 D SCA 1092629 Approved 20/05/2013 - 15:20
PEN RTU 2 NNI G 07/10/2020 - 09:00 07/10/2020 - 14:00 D SCA 1094573 Approved 20/05/2013 - 15:20
WHU RTU 1 NNI G 23/09/2020 - 10:00 23/09/2020 - 16:00 D SCA 1091136 Approved 07/05/2012 - 15:49
HEP RTU 1 NNI G 22/10/2020 - 10:00 22/10/2020 - 14:00 D SCA 1095193 Approved 07/05/2012 - 15:49
BOB RTU 1 NNI G 23/09/2020 - 09:00 23/09/2020 - 18:00 D SCA 1092728 Approved 07/05/2012 - 15:49
BOB RTU 1 NNI G 09/10/2020 - 09:00 09/10/2020 - 18:00 D SCA 1092732 Approved 07/05/2012 - 15:49
BOB RTU 1 NNI G 07/10/2020 - 09:00 07/10/2020 - 18:00 D SCA 1092731 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.