Outage planning results

Last updated: Sat, 08/08/2020 - 12:40
Your current search

Sites: all sites selected

Outages search found 4034 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
ROT TRK 2 NNI G 12/04/2021 - 07:30 16/04/2021 - 18:30 C RS 1085856 Approved 07/05/2012 - 15:49
ROT TRK 2 NNI G 09/03/2021 - 06:00 12/03/2021 - 18:00 C RS 1094734 Approved 07/05/2012 - 15:49
ROT WHE 1 NNI G 12/04/2021 - 07:30 16/04/2021 - 18:30 C RS 1092958 Approved 07/05/2012 - 15:49
ROT WHE 1 NNI G 11/08/2020 - 07:00 14/08/2020 - 16:00 C RS 1094703 Approved 07/05/2012 - 15:49
TAK T5 NNI G 06/12/2021 - 07:30 11/12/2021 - 18:30 C RS 1085161 Approved 07/05/2012 - 15:49
TAK T5 NNI G 01/11/2021 - 07:30 06/11/2021 - 18:30 C RS 1085159 Approved 07/05/2012 - 15:49
TAK T5 NNI G 04/10/2021 - 07:30 09/10/2021 - 18:30 C RS 1085157 Approved 07/05/2012 - 15:49
TAK T8 NNI G 11/10/2021 - 07:30 16/10/2021 - 18:30 C RS 1085163 Approved 07/05/2012 - 15:49
TAK T8 NNI G 13/12/2021 - 07:30 18/12/2021 - 18:30 C RS 1085167 Approved 07/05/2012 - 15:49
TAK T8 NNI G 08/11/2021 - 07:30 13/11/2021 - 18:30 C RS 1085165 Approved 07/05/2012 - 15:49
TAK T8 NNI G 12/08/2020 - 07:00 14/08/2020 - 19:00 C RS 1087948 Approved 07/05/2012 - 15:49
TGA T1 NNI G 24/11/2020 - 06:30 26/11/2020 - 18:30 C RS 1095044 Approved 07/05/2012 - 15:49
TGA T1 NNI G 09/04/2021 - 08:00 09/04/2021 - 16:00 D RS 1094093 Approved 07/05/2012 - 15:49
TGA T1 NNI G 05/08/2020 - 08:00 20/08/2020 - 18:00 C RS 1090554 Released 07/05/2012 - 15:49
TGA T2 NNI G 17/11/2020 - 06:30 19/11/2020 - 18:30 C RS 1095063 Approved 07/05/2012 - 15:49
TGA T3 NNI G 19/10/2020 - 07:30 23/10/2020 - 18:30 C RS 1088671 Approved 07/05/2012 - 15:49
TGA T3 NNI G 11/01/2021 - 07:30 15/01/2021 - 19:00 C RS 1085887 Approved 07/05/2012 - 15:49
TGA T4 NNI G 12/10/2020 - 07:30 16/10/2020 - 18:30 C RS 1085888 Approved 07/05/2012 - 15:49
TMI T1 NNI G 19/02/2021 - 08:00 19/02/2021 - 15:00 D RS 1094241 Approved 07/05/2012 - 15:49
TMU FDR 25 NNI L 12/02/2021 - 09:00 12/02/2021 - 15:00 D RS 1085897 Approved 07/05/2012 - 15:49
TMU FDR 26 NNI L 12/02/2021 - 09:00 12/02/2021 - 15:00 D RS 1085898 Approved 07/05/2012 - 15:49
TMU FDR 27 NNI L 12/02/2021 - 09:00 12/02/2021 - 15:00 D RS 1085899 Approved 07/05/2012 - 15:49
TMU FDR 28 NNI L 12/02/2021 - 09:00 12/02/2021 - 15:00 D RS 1085900 Approved 07/05/2012 - 15:49
TMU FDR 29 NNI L 12/02/2021 - 09:00 12/02/2021 - 15:00 D RS 1085901 Approved 07/05/2012 - 15:49
TMU FDR 23 NNI L 01/06/2021 - 07:30 04/06/2021 - 18:00 D RS 1085896 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.