Outage planning results

Last updated: Wed, 16/06/2021 - 09:40
Your current search

Sites: all sites selected

Outages search found 3524 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
NMA GOR TMH 2 SI G 04/10/2021 - 07:30 08/10/2021 - 18:30 C RS 1100372 Approved 22/09/2017 - 07:51
OKN T2 SNI G 06/03/2022 - 09:00 06/03/2022 - 16:00 D RS 1101077 Approved 05/06/2015 - 14:44
EDG T4 NNI G 06/10/2021 - 07:30 08/10/2021 - 16:00 C RS 1105386 Approved 07/05/2012 - 15:49
EDG T7 NNI G 23/11/2021 - 07:30 03/12/2021 - 18:30 C RS 1103115 Approved 07/05/2012 - 15:49
EDG TRK 1 NNI G 06/12/2021 - 07:30 10/12/2021 - 18:30 C RS 1084880 Approved 07/05/2012 - 15:49
EDG TRK 1 NNI G 17/01/2022 - 07:30 21/01/2022 - 18:30 C RS 1084881 Approved 07/05/2012 - 15:49
EDG TRK 1 NNI G 01/11/2021 - 07:30 06/11/2021 - 18:30 C RS 1084879 Approved 07/05/2012 - 15:49
EDG TRK 2 NNI G 08/11/2021 - 07:30 13/11/2021 - 18:30 C RS 1084882 Approved 07/05/2012 - 15:49
EDG TRK 2 NNI G 24/01/2022 - 07:30 28/01/2022 - 18:30 C RS 1084884 Approved 07/05/2012 - 15:49
EDG TRK 2 NNI G 13/12/2021 - 07:30 17/12/2021 - 18:30 C RS 1084883 Approved 07/05/2012 - 15:49
EDG WAI 2 NNI G 21/11/2021 - 07:30 21/11/2021 - 18:00 D RS 1100603 Approved 07/05/2012 - 15:49
HWB FDR 2472 SI L 19/10/2021 - 07:30 19/10/2021 - 18:30 D RS 1103573 Approved 01/05/2018 - 10:44
GLN CB 658 NNI G 25/08/2021 - 07:00 27/08/2021 - 18:00 C RS 1104792 Approved 07/05/2012 - 15:49
GLN T4 NNI G 09/08/2021 - 07:00 09/08/2021 - 18:00 D RS 1100175 Approved 07/05/2012 - 15:49
GLN T4 NNI G 02/08/2021 - 07:00 05/08/2021 - 18:00 C RS 1104606 Approved 07/05/2012 - 15:49
GLN T4 NNI G 04/04/2022 - 07:00 04/04/2022 - 18:00 D RS 1101235 Approved 07/05/2012 - 15:49
GLN T5 NNI G 06/04/2022 - 07:00 06/04/2022 - 18:00 D RS 1101266 Approved 07/05/2012 - 15:49
GLN T5 NNI G 11/08/2021 - 07:00 11/08/2021 - 18:00 D RS 1100203 Approved 07/05/2012 - 15:49
GLN T5 NNI G 08/12/2021 - 07:00 08/12/2021 - 18:00 D RS 1100702 Approved 07/05/2012 - 15:49
GLN T5 NNI G 08/11/2021 - 07:00 11/11/2021 - 18:00 C RS 1104595 Approved 07/05/2012 - 15:49
GLN T6 NNI G 11/10/2021 - 07:30 14/10/2021 - 18:00 C RS 1104591 Approved 07/05/2012 - 15:49
GLN T6 NNI G 10/12/2021 - 07:00 10/12/2021 - 18:00 D RS 1100721 Approved 07/05/2012 - 15:49
GLN T6 NNI G 13/08/2021 - 07:00 13/08/2021 - 18:00 D RS 1100210 Approved 07/05/2012 - 15:49
HOB CB 138 NNI G 20/10/2021 - 07:30 20/10/2021 - 18:30 D RS 1100490 Approved 27/02/2013 - 11:55
STK FDR 2382 SI L 28/06/2021 - 07:30 28/06/2021 - 18:30 D RS 1103420 Approved 14/01/2013 - 09:45
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.