Outage planning results

Last updated: Mon, 21/09/2020 - 10:40
Your current search

Sites: all sites selected

Outages search found 4031 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
TIM T6 SI G 17/05/2021 - 07:30 21/05/2021 - 18:30 D RS 1087382 Approved 03/03/2014 - 08:55
TIM T8 SI G 12/10/2020 - 07:30 12/10/2020 - 18:00 D RS 1090613 Approved 07/05/2012 - 15:51
TIM T8 SI G 17/05/2021 - 07:30 21/05/2021 - 18:30 D RS 1087381 Approved 07/05/2012 - 15:51
TIM T8 SI G 17/10/2020 - 06:00 18/10/2020 - 18:00 C RS 1085063 Approved 07/05/2012 - 15:51
TIM T8 SI G 16/10/2020 - 07:30 16/10/2020 - 17:00 D RS 1090621 Approved 07/05/2012 - 15:51
TKR 127 174 184 SNI G 01/02/2021 - 07:00 02/02/2021 - 18:30 D RS 1086477 Approved 07/05/2012 - 15:52
TKR 137 VT2 SNI G 26/01/2021 - 07:00 27/01/2021 - 18:30 D RS 1086478 Approved 07/05/2012 - 15:52
TKR CB 138 SNI G 01/02/2021 - 07:00 02/02/2021 - 18:30 D RS 1086479 Approved 11/05/2015 - 08:22
TKR FDR 2152 SNI L 30/09/2020 - 08:00 30/09/2020 - 16:00 D RS 1096444 Approved 26/05/2015 - 13:40
TKR FDR 2262 SNI L 30/09/2020 - 08:00 30/09/2020 - 16:00 D RS 1096445 Approved 26/05/2015 - 13:44
TKR T1 SNI G 01/02/2021 - 07:00 02/02/2021 - 18:30 D RS 1086480 Approved 07/05/2012 - 15:52
TKR T2 SNI G 26/01/2021 - 07:00 27/01/2021 - 18:30 D RS 1086481 Approved 07/05/2012 - 15:52
TKR WIL 1 SNI G 26/01/2021 - 07:00 27/01/2021 - 18:30 D RS 1096104 Approved 07/05/2012 - 15:52
TKR WIL 1 SNI G 19/10/2020 - 07:00 22/10/2020 - 18:30 C RS 1086482 Approved 07/05/2012 - 15:52
TKR WIL 1 SNI G 13/01/2020 - 07:30 23/10/2020 - 18:00 C RS 1070921 Cancelled 07/05/2012 - 15:52
TKR WIL 2 SNI G 01/02/2021 - 07:00 02/02/2021 - 18:30 D RS 1096105 Approved 07/05/2012 - 15:52
TKR WIL 2 SNI G 27/10/2020 - 07:00 30/10/2020 - 18:30 C RS 1086483 Approved 07/05/2012 - 15:52
TKR WIL 2 SNI G 21/01/2020 - 07:30 22/10/2020 - 18:00 C RS 1070920 Cancelled 07/05/2012 - 15:52
TKU 1064 1074 1097 SNI L 30/03/2021 - 07:00 31/03/2021 - 18:00 C RS 1093158 Approved 07/05/2012 - 15:52
TKU 1077 1104 1114 SNI L 30/03/2021 - 07:00 31/03/2021 - 18:00 C RS 1093161 Approved 07/05/2012 - 15:52
TKU 220BS B SNI G 07/11/2020 - 08:00 07/11/2020 - 16:00 D OPE 1096263 Approved 07/05/2012 - 15:53
TKU CB 128 SNI G 07/11/2020 - 08:00 07/11/2020 - 16:00 D OPE 1096264 Approved 07/05/2012 - 15:52
TKU CB 128 SNI G 30/03/2021 - 07:00 31/03/2021 - 18:00 D RS 1093260 Approved 07/05/2012 - 15:52
TKU DIS 137 SNI G 20/10/2020 - 07:30 20/10/2020 - 18:30 D OPE 1086484 Approved 07/05/2012 - 15:53
TKU DIS 147 SNI G 20/10/2020 - 07:30 20/10/2020 - 18:30 D OPE 1086485 Approved 07/05/2012 - 15:53
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.