Outage planning results

Last updated: Wed, 19/02/2020 - 15:40
Your current search

Sites: all sites selected

Outages search found 3099 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
CCT 644 ATU POA SI G 19/03/2020 - 09:00 19/03/2020 - 16:00 D RS 1074001 Approved 07/05/2012 - 15:52
CCT 770 BWK RRD SI G 17/03/2020 - 07:30 17/03/2020 - 18:30 D RS 1069162 Approved 07/05/2012 - 15:52
CCT 85990 HAY WWD SNI G 26/03/2020 - 08:00 26/03/2020 - 18:00 D RS 1089582 Approved 29/03/2018 - 11:25
CCT 85990 HAY WWD SNI G 13/05/2020 - 08:00 13/05/2020 - 18:00 D RS 1089595 Approved 29/03/2018 - 11:25
CCT 8762 HAY OTB SI G 26/03/2020 - 08:00 26/03/2020 - 18:00 D RS 1089583 Approved 25/02/2016 - 15:10
CCT 8762 HAY OTB SI G 13/05/2020 - 08:00 13/05/2020 - 18:00 D RS 1089596 Approved 25/02/2016 - 15:10
CCT 8770 TKR HAY SNI G 13/05/2020 - 08:00 13/05/2020 - 18:00 D RS 1089597 Approved 11/09/2013 - 10:13
CCT 8770 TKR HAY SNI G 26/03/2020 - 08:00 26/03/2020 - 18:00 D RS 1089584 Approved 11/09/2013 - 10:13
CCT 892 MNU MPE NNI G 28/02/2020 - 08:00 28/02/2020 - 18:30 D RS 1088652 Approved 23/08/2017 - 10:34
CCT 892 MNU MPE NNI G 02/04/2020 - 08:00 02/04/2020 - 18:30 D RS 1088655 Approved 23/08/2017 - 10:34
CCT 892 MPE MNU NNI G 24/02/2020 - 10:00 24/02/2020 - 15:00 D RS 1070350 Approved 07/05/2012 - 15:49
CCT 9185 HAY TPB SNI G 13/05/2020 - 08:00 13/05/2020 - 18:00 D RS 1089594 Approved 23/08/2017 - 10:34
CCT 9185 HAY TPB SNI G 26/03/2020 - 08:00 26/03/2020 - 18:00 D RS 1089581 Approved 23/08/2017 - 10:34
CCT 935 HKI MNU NNI G 28/02/2020 - 08:00 28/02/2020 - 18:30 D RS 1088651 Approved 07/05/2012 - 15:49
CCT 935 HKI MNU NNI G 02/04/2020 - 08:00 02/04/2020 - 18:30 D RS 1088654 Approved 07/05/2012 - 15:49
CCT 936 HKI KOE NNI G 02/04/2020 - 08:00 02/04/2020 - 18:30 D RS 1088656 Approved 07/05/2012 - 15:49
CCT 936 HKI KOE NNI G 28/02/2020 - 08:00 28/02/2020 - 16:30 D RS 1087953 Approved 07/05/2012 - 15:49
CCT 936 HKI KOE NNI G 12/05/2020 - 10:00 13/05/2020 - 15:00 D RS 1070506 Approved 07/05/2012 - 15:49
CCT 9999 MISC NNI NNI G 24/02/2020 - 23:00 25/02/2020 - 01:00 C RS 1089763 Approved 23/08/2017 - 10:34
CML FKN 1 SI G 19/05/2020 - 07:30 21/05/2020 - 18:00 C RS 1088784 Approved 07/05/2012 - 15:51
CML FKN 2 SI G 12/05/2020 - 07:30 14/05/2020 - 18:00 C RS 1088781 Approved 07/05/2012 - 15:51
CML RTU 1 SI G 18/03/2020 - 14:00 18/03/2020 - 16:00 D RS 1089175 Approved 07/05/2012 - 15:51
CML RTU 1 SI G 21/04/2020 - 10:00 21/04/2020 - 14:00 D RS 1089177 Approved 07/05/2012 - 15:51
CML T5 SI G 19/05/2020 - 07:30 21/05/2020 - 18:00 C RS 1088783 Approved 07/05/2012 - 15:51
CML T8 SI G 12/05/2020 - 07:30 14/05/2020 - 18:00 C RS 1088780 Approved 07/05/2012 - 15:52
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.