Outage planning results

Last updated: Wed, 18/09/2019 - 10:40
Your current search

Sites: all sites selected

Outages search found 4312 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BPE PRM HAY 1 SNI G 24/02/2020 - 07:30 28/02/2020 - 18:00 D RS 1071058 Approved 16/10/2014 - 10:31
BPE PRM HAY 2 SNI G 02/03/2020 - 07:30 06/03/2020 - 18:00 D RS 1071059 Approved 16/10/2014 - 10:32
BPE REVM T9 SNI G 01/07/2019 - 07:30 26/12/2019 - 18:00 D RS 1070654 Cancelled 07/05/2012 - 15:53
BPE T10 SNI G 21/10/2019 - 07:30 23/10/2019 - 17:00 C RS 1081612 Approved 07/05/2012 - 15:52
BPE T15 SNI G 02/12/2019 - 08:00 02/12/2019 - 15:00 D RS 1082980 Approved 07/05/2012 - 15:52
BPE T15 SNI G 08/06/2020 - 07:00 16/06/2020 - 17:00 C RS 1082364 Approved 07/05/2012 - 15:52
BPE T15 SNI G 13/01/2020 - 07:30 13/01/2020 - 18:00 D RS 1071048 Approved 07/05/2012 - 15:52
BPE T16 SNI G 02/12/2019 - 08:00 02/12/2019 - 15:00 D RS 1082981 Approved 07/05/2012 - 15:52
BPE T16 SNI G 22/06/2020 - 07:00 30/06/2020 - 17:00 C RS 1082365 Approved 07/05/2012 - 15:52
BPE T2 SNI G 14/01/2020 - 07:30 14/01/2020 - 18:00 D RS 1071051 Cancelled 07/05/2012 - 15:52
BPE T2 SNI G 03/08/2020 - 07:30 07/08/2020 - 18:30 C RS 1080902 Approved 07/05/2012 - 15:52
BPE T3 SNI G 21/11/2019 - 07:30 22/11/2019 - 18:00 D RS 1071067 Approved 07/05/2012 - 15:52
BPE T3 SNI G 14/09/2020 - 07:30 18/09/2020 - 18:30 C RS 1080903 Approved 07/05/2012 - 15:52
BPE T3 SNI G 01/08/2019 - 07:30 27/12/2019 - 18:00 D RS 1070655 Cancelled 07/05/2012 - 15:52
BPE TKU 1 SNI G 19/11/2019 - 07:30 22/11/2019 - 18:00 D RS 1071380 Approved 07/05/2012 - 15:52
BPE TKU 1 SNI G 22/10/2019 - 07:30 05/11/2020 - 18:00 D RS 1070934 Cancelled 07/05/2012 - 15:52
BPE TKU 2 SNI G 12/02/2020 - 07:30 13/02/2020 - 18:00 D RS 1071379 Approved 07/05/2012 - 15:52
BPE TNG 1 SNI G 13/01/2020 - 07:30 15/01/2020 - 18:00 C RS 1071068 Approved 07/05/2012 - 15:52
BPE TWC LTN 1 SNI G 20/04/2020 - 07:30 21/04/2020 - 18:00 D RS 1071213 Approved 07/05/2012 - 15:53
BPE WDV 1 SNI G 04/11/2019 - 07:00 12/11/2019 - 17:00 C RS 1079399 Approved 07/05/2012 - 15:52
BPE WDV 1 SNI G 30/03/2020 - 07:30 03/04/2020 - 18:00 D RS 1071056 Approved 07/05/2012 - 15:52
BPE WDV 1 SNI G 26/10/2020 - 07:30 30/10/2020 - 18:30 C RS 1080908 Approved 07/05/2012 - 15:52
BPE WDV 2 SNI G 10/02/2020 - 07:00 11/02/2020 - 18:00 C RS 1071406 Approved 07/05/2012 - 15:52
BPE WDV 2 SNI G 18/11/2019 - 07:00 25/11/2019 - 17:00 C RS 1079404 Approved 07/05/2012 - 15:52
BPE WDV 2 SNI G 23/03/2020 - 07:30 27/03/2020 - 18:00 D RS 1071057 Approved 07/05/2012 - 15:52
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.