Outage planning results

Last updated: Sun, 26/09/2021 - 19:10
Your current search

Sites: all sites selected

Outages search found 3906 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BRY ISL GXP TIE 1 SI G 17/09/2021 - 11:00 08/10/2021 - 19:30 C OTH 1109071 Released 19/04/2021 - 12:43
BRY RTU MULTI SI G 17/03/2022 - 13:30 17/03/2022 - 16:00 D RS 1107023 Approved 07/05/2012 - 15:52
BRY RTU MULTI SI G 01/12/2021 - 08:30 01/12/2021 - 17:00 D RS 1106945 Approved 07/05/2012 - 15:52
BRY RTU MULTI SI G 29/04/2022 - 09:00 29/04/2022 - 11:30 D RS 1107025 Approved 07/05/2012 - 15:52
BRY RTU MULTI SI G 24/03/2022 - 09:00 24/03/2022 - 11:30 D RS 1101190 Approved 07/05/2012 - 15:52
BRY RTU MULTI SI G 18/05/2022 - 09:00 18/05/2022 - 11:30 D RS 1107027 Approved 07/05/2012 - 15:52
BRY RTU MULTI SI G 16/12/2021 - 09:00 16/12/2021 - 12:00 D RS 1106946 Approved 07/05/2012 - 15:52
BRY RTU MULTI SI G 27/01/2022 - 13:30 27/01/2022 - 16:00 D RS 1106949 Approved 07/05/2012 - 15:52
BRY RTU MULTI SI G 24/11/2021 - 09:00 24/11/2021 - 12:00 D RS 1106944 Approved 07/05/2012 - 15:52
BRY RTU MULTI SI G 04/05/2022 - 09:00 04/05/2022 - 11:30 D RS 1107026 Approved 07/05/2012 - 15:52
BRY RTU MULTI SI G 10/02/2022 - 13:30 10/02/2022 - 16:00 D RS 1107022 Approved 07/05/2012 - 15:52
BRY RTU MULTI SI G 20/01/2022 - 09:00 20/01/2022 - 11:30 D RS 1106948 Approved 07/05/2012 - 15:52
BRY T5 SI G 24/01/2022 - 07:30 28/01/2022 - 17:30 C RS 1101198 Approved 07/05/2012 - 15:51
BRY T7 SI G 05/10/2021 - 07:30 05/10/2021 - 17:30 D RS 1099399 Cancelled 14/08/2012 - 09:30
BRY T7 SI G 14/03/2022 - 07:30 18/03/2022 - 17:30 C RS 1101207 Approved 14/08/2012 - 09:30
BWK 110BS SI G 29/03/2022 - 07:30 30/03/2022 - 18:30 C RS 1101220 Approved 07/05/2012 - 15:51
BWK CB 172 SI G 29/03/2022 - 07:30 30/03/2022 - 18:30 C RS 1104426 Approved 03/05/2013 - 09:30
BWK HWB 1 SI G 29/03/2022 - 07:30 30/03/2022 - 18:30 C RS 1104231 Approved 07/05/2012 - 15:51
BWK HWB 1 SI G 08/02/2022 - 07:30 10/02/2022 - 18:30 C RS 1107268 Approved 07/05/2012 - 15:51
CBG 206 224 236 NNI G 15/03/2022 - 07:00 16/03/2022 - 18:00 D RS 1100218 Approved 07/05/2012 - 15:50
CBG RTU 1 NNI G 22/12/2021 - 10:00 22/12/2021 - 14:00 D SCA 1109108 Approved 07/05/2012 - 15:49
CBG T3 NNI G 15/03/2022 - 07:00 18/03/2022 - 18:00 C RS 1100220 Approved 07/05/2012 - 15:49
CBG T3 NNI G 20/10/2021 - 07:00 20/10/2021 - 17:00 D RS 1102809 Approved 07/05/2012 - 15:49
CBG T4 NNI G 28/03/2022 - 07:30 31/03/2022 - 18:30 C RS 1100328 Approved 07/05/2012 - 15:49
CBG T4 NNI G 03/05/2022 - 07:30 05/05/2022 - 18:30 D RS 1101339 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.