Outage planning results

Last updated: Tue, 19/10/2021 - 12:10
Your current search

Sites: all sites selected

Outages search found 3635 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
HWB FDR 2592 SI L 20/04/2022 - 07:30 22/04/2022 - 18:30 C RS 1101309 Approved 07/05/2012 - 15:52
HWB FDR 2592 SI L 18/11/2021 - 07:30 20/11/2021 - 17:00 C RS 1106082 Approved 07/05/2012 - 15:52
HWB FDR 2582 SI L 18/11/2021 - 07:30 20/11/2021 - 17:00 C RS 1106081 Approved 01/05/2018 - 10:33
HWB FDR 2572 SI L 11/04/2022 - 07:30 14/04/2022 - 18:30 C RS 1101295 Approved 07/05/2012 - 15:52
HWB FDR 2572 SI L 18/11/2021 - 07:30 20/11/2021 - 17:00 C RS 1106080 Approved 07/05/2012 - 15:52
HWB FDR 2552 SI L 28/10/2021 - 08:30 29/10/2021 - 16:00 C RS 1108944 Approved 07/05/2012 - 15:52
HWB FDR 2552 SI L 04/04/2022 - 07:30 08/04/2022 - 18:30 C RS 1101247 Approved 07/05/2012 - 15:52
HWB FDR 2552 SI L 24/11/2021 - 07:30 26/11/2021 - 17:00 C RS 1106093 Approved 07/05/2012 - 15:52
HWB FDR 2552 SI L 07/03/2022 - 07:30 07/03/2022 - 18:30 D RS 1105477 Approved 07/05/2012 - 15:52
HWB FDR 2532 SI L 28/03/2022 - 07:30 01/04/2022 - 18:30 C RS 1101222 Approved 07/05/2012 - 15:52
HWB FDR 2532 SI L 24/11/2021 - 07:30 26/11/2021 - 17:00 C RS 1106092 Approved 07/05/2012 - 15:52
HWB FDR 2532 SI L 01/11/2021 - 08:30 02/11/2021 - 18:30 C RS 1109561 Approved 07/05/2012 - 15:52
HWB FDR 2532 SI L 11/03/2022 - 07:30 11/03/2022 - 18:30 D RS 1105484 Approved 07/05/2012 - 15:52
HWB FDR 2522 SI L 24/03/2022 - 07:30 25/03/2022 - 18:30 C RS 1101211 Approved 07/05/2012 - 15:52
HWB FDR 2522 SI L 24/11/2021 - 07:30 26/11/2021 - 17:00 C RS 1106091 Approved 07/05/2012 - 15:52
HWB FDR 2512 SI L 24/11/2021 - 07:30 26/11/2021 - 17:00 C RS 1106090 Approved 07/05/2012 - 15:52
HWB FDR 2512 SI L 14/03/2022 - 07:30 18/03/2022 - 18:30 C RS 1101160 Approved 07/05/2012 - 15:52
HWB FDR 2472 SI L 27/10/2021 - 07:30 27/10/2021 - 18:30 D RS 1103573 Approved 01/05/2018 - 10:44
HWB FDR 2462 SI L 27/10/2021 - 07:30 27/10/2021 - 18:30 D RS 1103572 Approved 01/05/2018 - 10:43
HWB CB 2628 SI G 15/11/2021 - 07:30 17/11/2021 - 17:00 C RS 1106075 Approved 07/05/2012 - 15:52
HWB CB 2628 SI G 28/10/2021 - 07:30 28/10/2021 - 18:30 D RS 1105574 Approved 07/05/2012 - 15:52
HWB CB 2628 SI G 18/11/2021 - 07:30 20/11/2021 - 17:00 C RS 1106079 Approved 07/05/2012 - 15:52
HWB CB 2568 SI G 07/03/2022 - 07:30 11/03/2022 - 18:30 C RS 1101105 Approved 07/05/2012 - 15:52
HWB CB 2568 SI G 18/11/2021 - 07:30 20/11/2021 - 17:00 C RS 1106078 Approved 07/05/2012 - 15:52
HWB CB 2568 SI G 24/11/2021 - 07:30 26/11/2021 - 17:00 C RS 1106088 Approved 07/05/2012 - 15:52
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.