Outage planning results

Last updated: Wed, 27/01/2021 - 21:40
Your current search

Sites: all sites selected

Outages search found 2839 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BPE CB 608 SNI G 16/02/2021 - 06:00 16/02/2021 - 18:30 D RS 1097119 Approved 07/05/2012 - 15:52
ARA 220CBF SNI G 16/02/2021 - 07:30 16/02/2021 - 18:30 D RS 1094969 Approved 07/03/2019 - 11:47
ARA 220BZ SNI G 16/02/2021 - 07:30 16/02/2021 - 18:30 D RS 1094968 Approved 07/03/2019 - 11:45
BPE CB 648 SNI G 16/02/2021 - 06:00 16/02/2021 - 18:30 D RS 1086131 Approved 07/05/2012 - 15:52
BPE 583 707 SNI G 16/02/2021 - 06:00 16/02/2021 - 18:30 D RS 1086117 Approved 07/05/2012 - 15:52
BPE 687 723 SNI G 16/02/2021 - 06:00 16/02/2021 - 18:30 D OPE 1099805 Approved 07/05/2012 - 15:52
OTA WKM 1 NNI G 09/02/2021 - 07:00 16/02/2021 - 19:00 C RS 1089060 Approved 07/05/2012 - 15:49
OTA WKM 1 NNI G 10/02/2021 - 07:00 16/02/2021 - 19:00 D RS 1085784 Cancelled 07/05/2012 - 15:49
BPE 220BS CHANGE SNI G 16/02/2021 - 18:30 16/02/2021 - 19:30 D PSO 1099709 Approved 07/05/2012 - 15:53
SFD RTU MULTI SNI G 17/02/2021 - 11:00 17/02/2021 - 15:00 D SCA 1095881 Approved 16/02/2018 - 11:36
HWB TMH 1 SI G 15/02/2021 - 08:00 17/02/2021 - 16:00 C RS 1093692 Approved 07/05/2012 - 15:51
HWB FDR 2532 SI L 17/02/2021 - 08:30 17/02/2021 - 16:30 D RS 1099824 Approved 07/05/2012 - 15:52
SBK RTU 1 SI G 17/02/2021 - 08:00 17/02/2021 - 17:00 D RS 1098038 Approved 07/05/2012 - 15:51
MHO FDR 2192 SNI L 10/12/2020 - 18:00 17/02/2021 - 17:00 C RS 1089892 Released 31/01/2020 - 16:18
ISL C 16 SI G 17/02/2021 - 08:00 17/02/2021 - 17:30 D RS 1097831 Approved 07/05/2012 - 15:51
MPE CB 252 NNI G 15/02/2021 - 07:00 17/02/2021 - 17:59 C RS 1099900 Approved 07/05/2012 - 15:50
TKR FDR 2272 SNI L 08/02/2021 - 11:00 17/02/2021 - 18:00 C RS 1098657 Approved 26/05/2015 - 13:44
MDN MPE 2 NNI G 15/02/2021 - 07:00 17/02/2021 - 18:00 C RS 1096621 Approved 07/05/2012 - 15:49
KOE MPE 2 NNI G 15/02/2021 - 07:00 17/02/2021 - 18:00 C RS 1096620 Approved 07/05/2012 - 15:49
WRK T30 SNI G 16/02/2021 - 07:30 17/02/2021 - 18:00 D RS 1095199 Approved 07/05/2012 - 15:53
WRK CB 108 SNI G 17/02/2021 - 07:30 17/02/2021 - 18:00 D RS 1086548 Approved 07/05/2012 - 15:53
WRK 67 103 87 SNI G 17/02/2021 - 07:30 17/02/2021 - 18:00 D RS 1086545 Approved 07/05/2012 - 15:53
MPE FDR 262 NNI L 15/02/2021 - 07:00 17/02/2021 - 18:00 C RS 1085718 Approved 09/04/2013 - 08:50
MPE FDR 242 NNI L 15/02/2021 - 07:00 17/02/2021 - 18:00 C RS 1085717 Approved 09/04/2013 - 08:50
MPE CB 288 NNI G 15/02/2021 - 07:00 17/02/2021 - 18:00 C RS 1085706 Approved 10/03/2016 - 13:25
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.