Outage planning results

Last updated: Sat, 06/03/2021 - 18:40
Your current search

Sites: all sites selected

Outages search found 2326 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
SFD TMN 1 SNI G 22/03/2021 - 06:30 23/03/2021 - 18:30 D RS 1099110 Approved 07/05/2012 - 15:52
BAL BWK 1 SI G 20/03/2021 - 07:30 23/03/2021 - 18:30 C RS 1099941 Cancelled 07/05/2012 - 15:51
BAL BWK 1 SI G 20/03/2021 - 07:30 23/03/2021 - 18:30 C RS 1099940 Approved 07/05/2012 - 15:51
ASB BRY 1 SI G 22/03/2021 - 06:30 23/03/2021 - 18:30 C RS 1093322 Approved 07/05/2012 - 15:51
OTA PEN 2 NNI G 09/02/2021 - 07:30 23/03/2021 - 18:30 C RS 1096748 Released 07/05/2012 - 15:49
WKM 220BS C NNI G 23/03/2021 - 07:30 23/03/2021 - 18:30 D RS 1092534 Approved 07/05/2012 - 15:50
WKM CB 288 NNI G 23/03/2021 - 07:30 23/03/2021 - 18:30 D RS 1092536 Approved 07/05/2012 - 15:50
WKM CB 228 NNI G 23/03/2021 - 07:30 23/03/2021 - 18:30 D RS 1092535 Approved 07/05/2012 - 15:50
DRY HLY 1 NNI G 23/03/2021 - 07:30 23/03/2021 - 18:30 D RS 1094558 Approved 07/05/2012 - 15:50
WKO 110CBF NNI G 23/03/2021 - 07:30 23/03/2021 - 18:30 D RS 1101532 Approved 17/07/2020 - 08:05
ISL 66BS CHANGE SI G 24/03/2021 - 06:30 24/03/2021 - 07:30 D PSO 1102296 Approved 07/05/2012 - 15:51
BRK RTU 2 SNI G 24/03/2021 - 10:00 24/03/2021 - 14:00 D RS 1094349 Approved 07/05/2012 - 15:53
BRK RTU 1 SNI G 24/03/2021 - 10:00 24/03/2021 - 14:00 D RS 1094348 Approved 07/05/2012 - 15:52
CPK FDR 2242 SNI L 24/03/2021 - 08:00 24/03/2021 - 15:00 D RS 1099676 Approved 07/05/2012 - 15:53
CPK FDR 2282 SNI L 24/03/2021 - 08:00 24/03/2021 - 15:00 D RS 1099677 Approved 07/05/2012 - 15:53
AVI RTU 1 SI G 24/03/2021 - 09:00 24/03/2021 - 15:00 D RS 1099135 Approved 07/05/2012 - 15:51
HAY RTU 1 SNI G 24/03/2021 - 07:00 24/03/2021 - 17:00 D RS 1092770 Approved 07/05/2012 - 15:53
HAY RTU 2 SNI G 24/03/2021 - 07:00 24/03/2021 - 17:00 D RS 1092771 Approved 07/05/2012 - 15:53
ISL 66CBF SI G 24/03/2021 - 09:00 24/03/2021 - 17:00 D RS 1095195 Approved 07/05/2012 - 15:51
ISL 66BZ SI G 24/03/2021 - 09:00 24/03/2021 - 17:00 D RS 1095194 Approved 07/05/2012 - 15:51
PEN C 12 NNI G 22/03/2021 - 07:00 24/03/2021 - 17:00 C RS 1096999 Approved 07/05/2012 - 15:50
MPE RTU 1 NNI G 24/03/2021 - 08:00 24/03/2021 - 17:00 D SCA 1099506 Approved 07/05/2012 - 15:49
MPE RTU 2 NNI G 24/03/2021 - 08:00 24/03/2021 - 17:00 D SCA 1099507 Approved 07/05/2012 - 15:50
WGN CB 92 SNI G 24/03/2021 - 07:30 24/03/2021 - 17:30 D RS 1099466 Approved 07/05/2012 - 15:53
ISL CB 628 SI G 24/03/2021 - 06:30 24/03/2021 - 17:30 D RS 1102341 Approved 07/05/2012 - 15:51
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.