Outage planning results

Last updated: Sun, 26/06/2022 - 18:10
Your current search

Sites: all sites selected

Outages search found 3436 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
HOR RTU 1 SI G 03/08/2022 - 07:30 03/08/2022 - 17:30 D RS 1103272 Approved 07/05/2012 - 15:51
TGA 110CBF NNI G 03/08/2022 - 07:00 03/08/2022 - 18:00 D RS 1112972 Approved 07/05/2012 - 15:50
TGA 110BZ NNI G 03/08/2022 - 07:00 03/08/2022 - 18:00 D RS 1112971 Approved 11/05/2017 - 11:27
OTA 22BZ NNI L 03/08/2022 - 07:00 03/08/2022 - 18:00 D RS 1109393 Approved 05/09/2012 - 14:50
OTA 22CBF NNI L 03/08/2022 - 07:00 03/08/2022 - 18:00 D RS 1109394 Approved 05/09/2012 - 14:50
OTA RTU 2 NNI G 03/08/2022 - 08:00 03/08/2022 - 18:30 D RS 1116983 Approved 07/05/2012 - 15:50
INV TWI 1 SI G 01/08/2022 - 08:00 04/08/2022 - 16:00 C RS 1116536 Approved 07/05/2012 - 15:51
CYD 220CBF SI G 02/08/2022 - 08:00 04/08/2022 - 17:00 D RS 1106519 Approved 07/05/2012 - 15:51
CYD 220BZ SI G 02/08/2022 - 08:00 04/08/2022 - 17:00 D RS 1106518 Approved 07/05/2012 - 15:51
PEN CB 798 NNI G 01/08/2022 - 07:00 04/08/2022 - 18:00 C RS 1115949 Approved 07/05/2012 - 15:50
PEN T11 NNI G 01/08/2022 - 07:00 04/08/2022 - 18:00 C RS 1115952 Approved 07/05/2012 - 15:49
PEN CB 2332B NNI G 01/08/2022 - 07:00 04/08/2022 - 18:00 C CLO 1117578 Approved 03/05/2016 - 09:04
PEN CB 2332A NNI G 01/08/2022 - 07:00 04/08/2022 - 18:00 C CLO 1117577 Approved 03/05/2016 - 09:02
PEN CB 812 NNI G 01/08/2022 - 07:00 04/08/2022 - 18:00 C RS 1115950 Approved 03/06/2014 - 14:18
PEN 220BS C NNI G 01/08/2022 - 07:00 04/08/2022 - 18:00 C RS 1115948 Approved 03/09/2013 - 15:10
PEN CB 828 NNI G 01/08/2022 - 07:00 04/08/2022 - 18:00 C RS 1115951 Approved 21/06/2013 - 09:50
OHB 220CBF SI G 04/08/2022 - 08:00 04/08/2022 - 18:30 D RS 1106667 Approved 07/05/2012 - 15:51
OHB 220BZ SI G 04/08/2022 - 08:00 04/08/2022 - 18:30 D RS 1106666 Approved 07/05/2012 - 15:51
CYD CB 508 SI G 02/08/2022 - 07:30 04/08/2022 - 18:30 C RS 1106515 Approved 07/05/2012 - 15:51
CYD CB 488 SI G 02/08/2022 - 07:30 04/08/2022 - 18:30 C RS 1106516 Approved 07/05/2012 - 15:51
CYD 220BS A SI G 02/08/2022 - 07:30 04/08/2022 - 18:30 C RS 1106517 Approved 07/05/2012 - 15:51
OTA 527 587 597 NNI G 04/08/2022 - 07:30 04/08/2022 - 18:30 D RS 1112976 Approved 07/05/2012 - 15:50
TAK RTU 1 NNI G 04/08/2022 - 07:30 04/08/2022 - 18:30 D RS 1116986 Approved 07/05/2012 - 15:49
OTA CB 598 NNI G 04/08/2022 - 07:30 04/08/2022 - 18:30 D RS 1112978 Approved 07/05/2012 - 15:49
OTA CB 528 NNI G 04/08/2022 - 07:30 04/08/2022 - 18:30 D RS 1112977 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.