Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
WKM CB 248 NNI G 24/11/2021 - 07:00 24/11/2021 - 17:30 D RS 1104284 Approved 07/05/2012 - 15:50
BRK CB 592 SNI G 23/11/2021 - 07:00 24/11/2021 - 18:00 C RS 1108839 Approved 07/05/2012 - 15:53
BRK CB 652 SNI G 23/11/2021 - 07:00 24/11/2021 - 18:00 C RS 1108838 Approved 07/05/2012 - 15:52
BRK CB 622 SNI G 23/11/2021 - 07:00 24/11/2021 - 18:00 C RS 1105422 Approved 07/05/2012 - 15:52
BRK 220BS B SNI G 23/11/2021 - 07:00 24/11/2021 - 18:00 C RS 1105423 Approved 07/05/2012 - 15:52
HTI FDR 222 NNI L 22/11/2021 - 07:30 24/11/2021 - 18:00 C RS 1097185 Approved 07/05/2012 - 15:49
CST 64 147 SNI G 24/11/2021 - 07:30 24/11/2021 - 18:30 D RS 1108580 Approved 07/05/2012 - 15:52
CST T4 SNI G 24/11/2021 - 07:30 24/11/2021 - 18:30 D RS 1108584 Approved 07/05/2012 - 15:52
CST MNI 1 SNI G 24/11/2021 - 07:30 24/11/2021 - 18:30 D RS 1108583 Approved 07/05/2012 - 15:52
CST HUI 2 SNI G 24/11/2021 - 07:30 24/11/2021 - 18:30 D RS 1108582 Approved 07/05/2012 - 15:52
CST CB 128 SNI G 24/11/2021 - 07:30 24/11/2021 - 18:30 D RS 1108581 Approved 07/05/2012 - 15:52
TWZ FDR 6312 SI L 22/11/2021 - 07:30 24/11/2021 - 18:30 C RS 1105046 Approved 07/05/2012 - 15:51
TKA T6 SI G 22/11/2021 - 06:30 24/11/2021 - 18:30 C RS 1100663 Approved 07/05/2012 - 15:51
ABY TKA 1 SI G 22/11/2021 - 06:30 24/11/2021 - 18:30 C RS 1100664 Approved 07/05/2012 - 15:51
TMU FDR 2842 NNI L 17/11/2021 - 07:30 24/11/2021 - 18:30 C RS 1108049 Approved 07/05/2012 - 15:50
TMU FDR 2832 NNI L 17/11/2021 - 07:30 24/11/2021 - 18:30 C RS 1108048 Approved 07/05/2012 - 15:50
TMU FDR 2822 NNI L 17/11/2021 - 07:30 24/11/2021 - 18:30 C RS 1108047 Approved 07/05/2012 - 15:50
TMU CB 2812 NNI L 17/11/2021 - 07:30 24/11/2021 - 18:30 C RS 1108045 Approved 07/05/2012 - 15:50
TMU FDR 2802 NNI L 17/11/2021 - 07:30 24/11/2021 - 18:30 C RS 1108046 Approved 07/05/2012 - 15:50
TMU CB 2798 NNI L 17/11/2021 - 07:30 24/11/2021 - 18:30 C RS 1108044 Approved 07/05/2012 - 15:50
TMU 11BS B2 NNI L 17/11/2021 - 07:30 24/11/2021 - 18:30 C RS 1108043 Approved 07/05/2012 - 15:50
HEN HEP 2 NNI G 22/11/2021 - 07:30 24/11/2021 - 18:30 C RS 1100613 Approved 07/05/2012 - 15:49
CST 33BS L SNI L 24/11/2021 - 07:30 24/11/2021 - 18:30 D RS 1108623 Approved 29/05/2019 - 12:08
CST SFD 3 SNI G 24/11/2021 - 07:30 24/11/2021 - 18:30 D RS 1108585 Approved 16/11/2018 - 14:41
CST CB 2188 SNI G 24/11/2021 - 07:30 24/11/2021 - 18:30 D RS 1108624 Approved 14/11/2018 - 14:40
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.