Outage planning results

Last updated: Wed, 18/05/2022 - 21:40
Your current search

Sites: all sites selected

Outages search found 3588 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
TWI CB 428 SI G 02/08/2022 - 07:30 02/08/2022 - 17:30 D RS 1116539 Approved 07/05/2012 - 15:51
TWI 220BS A SI G 02/08/2022 - 07:30 02/08/2022 - 17:30 D RS 1116538 Approved 07/05/2012 - 15:51
TRK CB 618 NNI G 01/08/2022 - 07:00 02/08/2022 - 18:00 C RS 1112963 Approved 14/08/2014 - 09:45
OTA 220CBF 2 NNI G 02/08/2022 - 07:00 02/08/2022 - 18:00 D RS 1109392 Approved 07/05/2012 - 15:50
OTA 220BZ 2 NNI G 02/08/2022 - 07:00 02/08/2022 - 18:00 D RS 1109391 Approved 07/05/2012 - 15:50
TRK DIS 407 NNI G 01/08/2022 - 07:00 02/08/2022 - 18:00 C CLO 1116354 Approved 07/05/2012 - 15:50
KMO TMI 1 NNI G 01/08/2022 - 07:00 02/08/2022 - 18:00 C OPE 1116355 Approved 07/05/2012 - 15:50
KMO TRK 1 NNI G 01/08/2022 - 07:00 02/08/2022 - 18:00 C RS 1112962 Approved 07/05/2012 - 15:50
TRK 567 607 627 NNI G 01/08/2022 - 07:00 02/08/2022 - 18:00 C RS 1112961 Approved 07/05/2012 - 15:49
TWI FDR 482 SI L 03/08/2022 - 07:30 03/08/2022 - 17:30 D RS 1116544 Approved 07/05/2012 - 15:51
TWI CB 478 SI G 03/08/2022 - 07:30 03/08/2022 - 17:30 D RS 1116543 Approved 07/05/2012 - 15:51
TWI CB 468 SI G 03/08/2022 - 07:30 03/08/2022 - 17:30 D RS 1116545 Approved 07/05/2012 - 15:51
TWI 220BS D SI G 03/08/2022 - 07:30 03/08/2022 - 17:30 D RS 1116542 Approved 07/05/2012 - 15:51
HOR RTU 1 SI G 03/08/2022 - 07:30 03/08/2022 - 17:30 D RS 1103272 Approved 07/05/2012 - 15:51
OTA 22BZ NNI L 03/08/2022 - 07:00 03/08/2022 - 18:00 D RS 1109393 Approved 05/09/2012 - 14:50
OTA 22CBF NNI L 03/08/2022 - 07:00 03/08/2022 - 18:00 D RS 1109394 Approved 05/09/2012 - 14:50
TGA 110CBF NNI G 03/08/2022 - 07:00 03/08/2022 - 18:00 D RS 1112972 Approved 07/05/2012 - 15:50
TGA 110BZ NNI G 03/08/2022 - 07:00 03/08/2022 - 18:00 D RS 1112971 Approved 11/05/2017 - 11:27
INV TWI 1 SI G 01/08/2022 - 08:00 04/08/2022 - 16:00 C RS 1116536 Approved 07/05/2012 - 15:51
CYD 220CBF SI G 02/08/2022 - 08:00 04/08/2022 - 17:00 D RS 1106519 Approved 07/05/2012 - 15:51
CYD 220BZ SI G 02/08/2022 - 08:00 04/08/2022 - 17:00 D RS 1106518 Approved 07/05/2012 - 15:51
PEN 220BS C NNI G 01/08/2022 - 07:00 04/08/2022 - 18:00 C RS 1115948 Approved 03/09/2013 - 15:10
PEN CB 828 NNI G 01/08/2022 - 07:00 04/08/2022 - 18:00 C RS 1115951 Approved 21/06/2013 - 09:50
PEN CB 812 NNI G 01/08/2022 - 07:00 04/08/2022 - 18:00 C RS 1115950 Approved 03/06/2014 - 14:18
PEN CB 798 NNI G 01/08/2022 - 07:00 04/08/2022 - 18:00 C RS 1115949 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.