Outage planning results

Last updated: Fri, 20/05/2022 - 16:10
Your current search

Sites: all sites selected

Outages search found 3581 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
CUL T22 SI G 01/05/2023 - 08:00 05/05/2023 - 17:00 C RS 1113925 Approved 07/05/2012 - 15:52
STU RTU 1 SI G 03/05/2023 - 07:30 05/05/2023 - 16:00 D RS 1116278 Approved 07/05/2012 - 15:51
OPK KPI SFD 2 SNI G 05/05/2023 - 01:00 05/05/2023 - 16:00 C RS 1112768 Approved 07/05/2012 - 15:52
OPK T4 SNI G 05/05/2023 - 01:00 05/05/2023 - 16:00 C RS 1112820 Approved 07/05/2012 - 15:52
KPI SFD 2 SNI G 17/04/2023 - 08:00 05/05/2023 - 16:00 C RS 1112657 Approved 13/12/2012 - 08:15
OPK SFD 1 SNI G 05/05/2023 - 01:00 05/05/2023 - 02:00 C RS 1112815 Approved 07/05/2012 - 15:52
OPK T5 SNI G 05/05/2023 - 01:00 05/05/2023 - 02:00 C RS 1112822 Approved 07/05/2012 - 15:52
OPK FDR 1102 SNI L 05/05/2023 - 01:00 05/05/2023 - 02:00 C RS 1112725 Approved 07/05/2012 - 15:53
OPK FDR 1142 SNI L 05/05/2023 - 01:00 05/05/2023 - 02:00 C RS 1112729 Approved 07/05/2012 - 15:53
OPK DIS 67 SNI G 18/04/2023 - 01:00 05/05/2023 - 02:00 C CLO 1112719 Approved 07/05/2012 - 15:53
OPK DIS 77 SNI G 18/04/2023 - 01:00 05/05/2023 - 02:00 C CLO 1112720 Approved 07/05/2012 - 15:53
OTA SWN 1 NNI G 01/05/2023 - 07:00 04/05/2023 - 18:00 C RS 1113477 Approved 07/05/2012 - 15:49
PEN T10 NNI G 01/05/2023 - 07:00 04/05/2023 - 18:00 C OPE 1113480 Approved 07/05/2012 - 15:49
PEN CB 8612 NNI G 01/05/2023 - 07:00 04/05/2023 - 18:00 C OPE 1113479 Approved 17/03/2014 - 11:42
PTS 270598 MAN ROX SI G 04/05/2023 - 07:30 04/05/2023 - 17:00 D RS 1113929 Approved 24/02/2015 - 13:48
EDG TRK 2 NNI G 01/05/2023 - 07:30 02/05/2023 - 18:30 C RS 1113483 Approved 07/05/2012 - 15:49
TRK 347 357 417 NNI G 01/05/2023 - 07:30 02/05/2023 - 18:30 C RS 1113481 Approved 07/05/2012 - 15:49
TRK 407 417 437 NNI G 01/05/2023 - 07:30 02/05/2023 - 18:30 C RS 1113482 Approved 07/05/2012 - 15:50
TRK CB 142 NNI G 01/05/2023 - 07:30 02/05/2023 - 18:30 C OPE 1116682 Approved 07/05/2012 - 15:50
PTS 1409 FHL RDF SNI G 02/05/2023 - 08:00 02/05/2023 - 18:30 D RS 1112738 Approved 07/05/2012 - 15:53
TRK T2 NNI G 01/05/2023 - 07:30 02/05/2023 - 18:30 C RS 1113484 Approved 15/05/2012 - 15:35
DRY 220BZ A1 NNI G 02/05/2023 - 07:30 02/05/2023 - 18:30 D RS 1113485 Approved 10/04/2014 - 13:13
INV TWI 2 SI G 24/04/2023 - 07:30 29/04/2023 - 18:30 C RS 1104090 Approved 07/05/2012 - 15:51
HAM PAO WHU 2 NNI G 17/04/2023 - 07:30 28/04/2023 - 18:30 C RS 1113441 Approved 07/05/2012 - 15:49
MPE CB 252 NNI G 24/04/2023 - 07:30 28/04/2023 - 18:30 C OPE 1113471 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.