Outage planning results

Last updated: Thu, 06/05/2021 - 19:40
Your current search

Sites: all sites selected

Outages search found 3569 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
OTA FDR 2752 NNI L 16/10/2021 - 08:00 16/10/2021 - 16:00 D RS 1100461 Approved 07/05/2012 - 15:50
BPE PRM HAY 2 SNI G 18/10/2021 - 06:00 22/10/2021 - 18:00 C RS 1100462 Approved 16/10/2014 - 10:32
PRM T2 SNI G 18/10/2021 - 06:00 22/10/2021 - 18:00 C RS 1098985 Cancelled 09/07/2014 - 08:34
PRM T2 SNI G 18/10/2021 - 06:00 22/10/2021 - 18:00 C RS 1100463 Approved 09/07/2014 - 08:34
ISL TKB 1 SI G 18/10/2021 - 06:30 22/10/2021 - 18:30 C RS 1100295 Approved 07/05/2012 - 15:51
PEN CB 848 NNI G 18/10/2021 - 07:00 19/10/2021 - 18:30 C RS 1100465 Approved 25/11/2013 - 15:55
HOB PEN 1 NNI G 18/10/2021 - 07:00 19/10/2021 - 18:30 C RS 1100469 Approved 27/02/2013 - 11:55
PEN 220BS D NNI G 18/10/2021 - 07:00 19/10/2021 - 18:30 C RS 1100464 Approved 03/09/2013 - 15:15
PAK PEN 3 NNI G 18/10/2021 - 07:00 19/10/2021 - 18:30 C RS 1100468 Approved 03/09/2013 - 14:55
PEN CB 828 NNI G 18/10/2021 - 07:00 19/10/2021 - 18:30 C RS 1100470 Approved 21/06/2013 - 09:50
PEN 697 847 NNI G 18/10/2021 - 07:00 19/10/2021 - 18:30 C RS 1100466 Approved 05/06/2014 - 15:05
HAY CB 982A HVDC H 18/10/2021 - 07:00 22/10/2021 - 18:30 C RS 1100471 Approved 15/08/2012 - 11:40
HAY F 5 HVDC H 18/10/2021 - 07:00 22/10/2021 - 18:30 C RS 1100472 Approved 15/08/2012 - 11:40
MNI MKE SFD 1 SNI G 18/10/2021 - 07:00 18/10/2021 - 18:00 D RS 1103048 Approved 07/05/2012 - 15:52
WKM RTU 1 NNI G 18/10/2021 - 07:00 20/10/2021 - 17:30 D RS 1102837 Approved 07/05/2012 - 15:49
PEN CB 698 NNI G 18/10/2021 - 07:00 19/10/2021 - 18:30 C RS 1100467 Approved 10/09/2014 - 13:12
PEN T10 NNI G 18/10/2021 - 07:00 19/10/2021 - 18:30 C OPE 1101921 Approved 07/05/2012 - 15:49
TMN 396 457 SNI G 18/10/2021 - 07:30 22/10/2021 - 17:30 C RS 1100474 Approved 07/05/2012 - 15:52
TMN CB 458 SNI G 18/10/2021 - 07:30 22/10/2021 - 17:30 C RS 1100475 Approved 07/05/2012 - 15:52
TMN T5 SNI G 18/10/2021 - 07:30 22/10/2021 - 17:30 C RS 1100476 Approved 07/05/2012 - 15:52
SFD TMN 1 SNI G 18/10/2021 - 07:30 22/10/2021 - 17:30 C RS 1100473 Approved 07/05/2012 - 15:52
KIK STC 2 HVDC G 18/10/2021 - 07:30 18/10/2021 - 18:30 D RS 1100485 Cancelled 07/05/2012 - 15:52
KIK STC 2 HVDC G 18/10/2021 - 07:30 24/10/2021 - 18:30 C RS 1095992 Approved 07/05/2012 - 15:52
KIK STC 2B HVDC G 18/10/2021 - 07:30 24/10/2021 - 18:30 C RS 1095994 Approved 07/05/2012 - 15:52
KIK STC 2A HVDC G 18/10/2021 - 07:30 24/10/2021 - 18:30 C RS 1095993 Approved 07/05/2012 - 15:52
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.