Outage planning results

Last updated: Fri, 24/09/2021 - 16:10
Your current search

Sites: all sites selected

Outages search found 3924 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
WIL 110BS C PROT2 SNI G 03/10/2021 - 08:00 03/10/2021 - 17:00 D RS 1108301 Approved 25/08/2021 - 11:24
WIL 110BS C PROT1 SNI G 03/10/2021 - 08:00 03/10/2021 - 17:00 D RS 1108302 Approved 25/08/2021 - 11:23
BPE 220CBF SNI G 03/10/2021 - 08:00 03/10/2021 - 16:00 D RS 1105411 Approved 07/05/2012 - 15:53
WIL 110BS A PROT2 SNI G 03/10/2021 - 08:00 03/10/2021 - 17:00 D RS 1108299 Cancelled 25/08/2021 - 11:23
WIL 110BS A PROT1 SNI G 03/10/2021 - 08:00 03/10/2021 - 17:00 D RS 1108297 Cancelled 25/08/2021 - 11:09
WIL 220CBF SNI G 03/10/2021 - 08:00 03/10/2021 - 16:00 D RS 1098679 Approved 07/05/2012 - 15:53
BEN HAY 1 HVDC H 03/10/2021 - 08:00 03/10/2021 - 19:00 D RCB 1109033 Approved 07/05/2012 - 15:49
BEN HAY 2 HVDC H 03/10/2021 - 08:00 03/10/2021 - 19:00 D RCB 1109034 Approved 07/05/2012 - 15:49
BPE 220BZ SNI G 03/10/2021 - 08:00 03/10/2021 - 16:00 D RS 1105410 Approved 07/05/2012 - 15:52
WIL 220BZ SNI G 03/10/2021 - 08:00 03/10/2021 - 16:00 D RS 1098678 Approved 07/05/2012 - 15:52
CPK FDR 2232 SNI L 02/10/2021 - 09:00 02/10/2021 - 15:00 D RS 1108625 Approved 07/05/2012 - 15:53
BEN HAY 1 HVDC H 02/10/2021 - 08:00 02/10/2021 - 19:00 D RCB 1109025 Approved 07/05/2012 - 15:49
BEN HAY 2 HVDC H 02/10/2021 - 08:00 02/10/2021 - 19:00 D RCB 1109032 Approved 07/05/2012 - 15:49
OKI RTU 2 SNI G 02/10/2021 - 07:30 02/10/2021 - 17:00 D RS 1098973 Cancelled 07/05/2012 - 15:53
OKI 220BZ A SNI G 02/10/2021 - 07:30 02/10/2021 - 17:00 D RS 1098956 Cancelled 07/05/2012 - 15:52
OKI 220BZ B SNI G 02/10/2021 - 07:30 02/10/2021 - 17:00 D RS 1098962 Cancelled 07/05/2012 - 15:52
OKI RTU 1 SNI G 02/10/2021 - 07:30 02/10/2021 - 17:00 D RS 1098971 Cancelled 07/05/2012 - 15:52
STU DIS 76 SI G 02/10/2021 - 06:30 03/10/2021 - 18:30 C OPE 1109159 Approved 07/05/2012 - 15:52
ASB 347 296 SI G 02/10/2021 - 06:30 03/10/2021 - 18:30 C RS 1105639 Approved 07/05/2012 - 15:51
ASB TIM TWZ 1 SI G 02/10/2021 - 06:30 03/10/2021 - 18:30 C RS 1100357 Approved 07/05/2012 - 15:51
ASB T8 SI G 02/10/2021 - 06:30 03/10/2021 - 18:30 C RS 1105641 Approved 07/05/2012 - 15:51
ASB T1 SI G 02/10/2021 - 06:30 03/10/2021 - 18:30 C RS 1105640 Approved 07/05/2012 - 15:51
TIM T5 SI G 02/10/2021 - 06:30 03/10/2021 - 18:30 C RS 1100358 Approved 07/05/2012 - 15:51
BRK WGN GXP TIE SNI G 02/10/2021 - 00:30 02/10/2021 - 02:30 D OTH 1109178 Approved 01/11/2013 - 08:16
KIK 220BS CHANGE SI G 01/10/2021 - 18:30 01/10/2021 - 19:00 D PSO 1108875 Approved 07/05/2012 - 15:51
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.