Outage planning results

Last updated: Mon, 20/09/2021 - 16:40
Your current search

Sites: all sites selected

Outages search found 3907 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BDE C 2 SI G 29/03/2022 - 08:00 31/03/2022 - 16:00 C RS 1104412 Approved 07/05/2012 - 15:51
BDE 11BZ SI L 29/03/2022 - 08:00 31/03/2022 - 16:00 D RS 1104414 Approved 07/05/2012 - 15:51
BDE FDR 14 SI L 29/03/2022 - 08:00 31/03/2022 - 16:00 C RS 1104408 Approved 07/05/2012 - 15:51
BDE FDR 15 SI L 29/03/2022 - 08:00 31/03/2022 - 16:00 C RS 1104409 Approved 07/05/2012 - 15:51
BDE FDR 16 SI L 29/03/2022 - 08:00 31/03/2022 - 16:00 C RS 1104410 Approved 07/05/2012 - 15:51
HAY 11BZ AB HVDC H 29/03/2022 - 08:00 29/03/2022 - 17:00 D RS 1107961 Approved 05/11/2018 - 09:18
HAY 11CBF AB HVDC H 29/03/2022 - 08:00 29/03/2022 - 17:00 D RS 1107962 Approved 05/11/2018 - 09:51
BAL BWK 1 SI G 29/03/2022 - 07:30 30/03/2022 - 18:30 C RS 1104230 Approved 07/05/2012 - 15:51
OHB 220CBF SI G 29/03/2022 - 07:30 29/03/2022 - 18:30 D RS 1106676 Approved 07/05/2012 - 15:51
BWK 110BS SI G 29/03/2022 - 07:30 30/03/2022 - 18:30 C RS 1101220 Approved 07/05/2012 - 15:51
BWK HWB 1 SI G 29/03/2022 - 07:30 30/03/2022 - 18:30 C RS 1104231 Approved 07/05/2012 - 15:51
OHB 220BZ SI G 29/03/2022 - 07:30 29/03/2022 - 18:30 D RS 1106675 Approved 07/05/2012 - 15:51
BWK CB 172 SI G 29/03/2022 - 07:30 30/03/2022 - 18:30 C RS 1104426 Approved 03/05/2013 - 09:30
HAY FDR 2822 SNI L 29/03/2022 - 07:30 01/04/2022 - 17:00 C RS 1100905 Approved 07/05/2012 - 15:53
ARI CB 82 BZ NNI G 28/03/2022 - 09:00 01/04/2022 - 11:00 C RS 1106890 Approved 07/05/2012 - 15:50
MPE CB 292 NNI G 28/03/2022 - 07:30 01/04/2022 - 18:29 C OPE 1085180 Approved 07/05/2012 - 15:50
EDG TRK 2 NNI G 28/03/2022 - 07:30 01/04/2022 - 18:30 C RS 1084883 Approved 07/05/2012 - 15:49
KIN TRK 1 NNI G 28/03/2022 - 07:30 29/03/2022 - 17:30 C RS 1107602 Approved 07/05/2012 - 15:49
MDN MPE 2 NNI G 28/03/2022 - 07:30 01/04/2022 - 18:30 C RS 1085178 Approved 07/05/2012 - 15:49
HEP C 12 NNI G 28/03/2022 - 07:30 11/04/2022 - 18:30 C RS 1103134 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 28/03/2022 - 07:30 01/04/2022 - 18:29 C OPE 1085179 Approved 07/05/2012 - 15:50
DOB RFN IGH 2 SI G 28/03/2022 - 07:30 01/04/2022 - 18:30 C RS 1100315 Approved 20/08/2018 - 12:38
BDE EDN 1 SI G 28/03/2022 - 07:30 29/03/2022 - 18:30 C RS 1101219 Approved 07/05/2012 - 15:51
DOB T11 SI G 28/03/2022 - 07:30 01/04/2022 - 18:30 C RS 1101336 Approved 07/05/2012 - 15:52
HWB FDR 2532 SI L 28/03/2022 - 07:30 01/04/2022 - 18:30 C RS 1101222 Approved 07/05/2012 - 15:52
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.