Outage planning results

Last updated: Wed, 18/09/2019 - 10:40
Your current search

Sites: all sites selected

Outages search found 4312 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
OTA T4 NNI G 13/01/2020 - 07:00 22/06/2020 - 16:00 C RS 1069034 Approved 07/05/2012 - 15:49
MNG FDR 1072 NNI L 17/02/2020 - 07:30 17/02/2020 - 18:30 D RS 1070337 Approved 07/05/2012 - 15:49
KPU WKO 1 NNI G 12/02/2020 - 07:30 12/02/2020 - 18:30 D RS 1083001 Approved 07/05/2012 - 15:49
KPO 77 87 NNI G 07/10/2019 - 07:30 07/10/2019 - 18:30 D RS 1077495 Approved 07/05/2012 - 15:49
WKO T1 NNI G 10/02/2020 - 07:30 08/03/2020 - 18:30 C RS 1070616 Approved 07/05/2012 - 15:49
OTA T3 NNI G 23/06/2020 - 07:30 26/06/2020 - 18:30 C RS 1070449 Approved 07/05/2012 - 15:49
WKO T1 NNI G 28/04/2020 - 07:30 01/05/2020 - 18:30 C RS 1070619 Approved 07/05/2012 - 15:49
WIR T2 NNI G 18/09/2019 - 07:30 21/09/2019 - 18:30 C RS 1070126 Released 07/05/2012 - 15:49
OTA T2 NNI G 03/10/2019 - 07:00 04/10/2019 - 18:30 D OPE 1083439 Approved 07/05/2012 - 15:49
MNG FDR 1062 NNI L 22/06/2020 - 07:30 22/06/2020 - 18:30 D RS 1070550 Approved 07/05/2012 - 15:49
WIR T2 NNI G 03/10/2019 - 07:30 04/10/2019 - 18:00 C RS 1070147 Approved 07/05/2012 - 15:49
WIR T1 NNI G 12/02/2020 - 07:30 13/02/2020 - 18:30 D RS 1070320 Approved 07/05/2012 - 15:49
OTA T2 NNI G 23/10/2019 - 07:00 23/10/2019 - 18:00 D OPE 1082508 Approved 07/05/2012 - 15:49
WIR T1 NNI G 20/01/2020 - 07:00 23/01/2020 - 16:00 C RS 1082545 Approved 07/05/2012 - 15:49
WIR FDR 2172 NNI L 21/09/2019 - 07:30 21/09/2019 - 18:30 D RS 1070130 Approved 07/05/2012 - 15:49
OTA T12 NNI G 08/11/2019 - 07:00 08/11/2019 - 16:00 D RS 1081993 Approved 07/05/2012 - 15:49
MDN MPE 2 NNI G 02/12/2019 - 07:30 03/12/2019 - 18:30 C RS 1081942 Approved 07/05/2012 - 15:49
KPU WKO 1 NNI G 14/01/2020 - 07:30 14/01/2020 - 18:30 D RS 1082933 Approved 07/05/2012 - 15:49
KPU T3 NNI G 23/09/2019 - 07:30 23/09/2019 - 18:30 D RS 1070623 Cancelled 07/05/2012 - 15:49
KPU T3 NNI G 19/11/2019 - 07:30 19/11/2019 - 18:00 D RS 1082734 Approved 07/05/2012 - 15:49
KPU LST 1 NNI L 03/12/2019 - 07:30 03/12/2019 - 18:00 D RS 1082741 Approved 07/05/2012 - 15:49
WIR FDR 2152 NNI L 21/09/2019 - 07:30 21/09/2019 - 18:30 D RS 1070129 Approved 07/05/2012 - 15:49
WIR FDR 2152 NNI L 15/11/2019 - 07:30 15/11/2019 - 18:30 D RS 1073898 Approved 07/05/2012 - 15:49
OTA T11 NNI G 10/11/2019 - 07:00 10/11/2019 - 16:00 D RS 1082005 Approved 07/05/2012 - 15:49
WIR FDR 2132 NNI L 21/09/2019 - 07:30 21/09/2019 - 18:30 D RS 1070128 Cancelled 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.