Outage planning results

Last updated: Wed, 16/10/2019 - 11:40
Your current search

Sites: all sites selected

Outages search found 4032 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
ROT RTU 1 NNI G 12/02/2020 - 08:00 12/02/2020 - 17:00 D RS 1083915 Approved 07/05/2012 - 15:49
ROT RTU 1 NNI G 01/04/2020 - 13:00 01/04/2020 - 17:00 D RS 1080548 Approved 07/05/2012 - 15:49
ROT RTU 1 NNI G 29/01/2020 - 08:00 29/01/2020 - 13:00 D SCA 1083910 Approved 07/05/2012 - 15:49
ROT RTU 1 NNI G 19/02/2020 - 08:00 19/02/2020 - 13:00 D SCA 1083921 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 30/01/2020 - 13:00 30/01/2020 - 17:00 D SCA 1080140 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 31/10/2019 - 13:00 31/10/2019 - 17:00 D SCA 1080125 Approved 07/05/2012 - 15:49
HAM 110BZ A NNI G 01/04/2020 - 07:30 01/04/2020 - 12:00 D RS 1082952 Approved 07/05/2012 - 15:49
HAM 110BZ A NNI G 07/12/2020 - 13:00 07/12/2020 - 17:00 D RS 1078677 Approved 07/05/2012 - 15:49
HAM 110BZ A NNI G 13/12/2020 - 08:30 13/12/2020 - 16:30 D RS 1078682 Approved 07/05/2012 - 15:49
HAM 110BZ A NNI G 22/11/2020 - 08:30 22/11/2020 - 16:30 D RS 1078673 Approved 07/05/2012 - 15:49
HAM 110BZ A NNI G 02/11/2020 - 08:30 02/11/2020 - 12:30 D RS 1078653 Approved 07/05/2012 - 15:49
HAM 110BZ A NNI G 08/11/2020 - 08:30 08/11/2020 - 16:30 D RS 1078658 Approved 07/05/2012 - 15:49
HAM 110BZ A NNI G 16/11/2020 - 08:30 16/11/2020 - 12:30 D RS 1078668 Approved 07/05/2012 - 15:49
HAM 110BZ A NNI G 27/02/2020 - 07:00 28/02/2020 - 18:00 D RS 1074260 Approved 07/05/2012 - 15:49
HAM 110BZ A NNI G 08/12/2019 - 07:30 08/12/2019 - 17:30 D RS 1074423 Approved 07/05/2012 - 15:49
HAM 110BZ A NNI G 29/11/2019 - 07:30 29/11/2019 - 12:00 D RS 1082255 Approved 07/05/2012 - 15:49
HAM 110BZ B NNI G 29/11/2019 - 07:30 29/11/2019 - 12:00 D RS 1082256 Approved 07/05/2012 - 15:49
HAM 110BZ B NNI G 08/12/2019 - 07:30 08/12/2019 - 17:30 D RS 1074424 Approved 07/05/2012 - 15:49
HAM 110BZ B NNI G 27/02/2020 - 07:00 28/02/2020 - 18:00 D RS 1074333 Approved 07/05/2012 - 15:49
HAM 110BZ B NNI G 16/11/2020 - 08:30 16/11/2020 - 12:30 D RS 1078669 Approved 07/05/2012 - 15:49
HAM 110BZ B NNI G 08/11/2020 - 08:30 08/11/2020 - 16:30 D RS 1078659 Approved 07/05/2012 - 15:49
HAM 110BZ B NNI G 02/11/2020 - 08:30 02/11/2020 - 12:30 D RS 1078654 Approved 07/05/2012 - 15:49
HAM 110BZ B NNI G 22/11/2020 - 08:30 22/11/2020 - 16:30 D RS 1078674 Approved 07/05/2012 - 15:49
MTM RTU 1 NNI G 26/11/2019 - 07:30 28/11/2019 - 18:30 D RS 1075096 Approved 07/05/2012 - 15:49
ARI CB 48 NNI G 18/04/2020 - 06:30 19/04/2020 - 18:30 D CLO 1078692 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.