Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
MHO RTU 1 SNI G 22/10/2020 - 08:00 22/10/2020 - 16:00 D RS 1089838 Approved 07/05/2012 - 15:52
MHO RTU 1 SNI G 17/08/2021 - 08:00 18/08/2021 - 16:00 D RS 1090069 Approved 07/05/2012 - 15:52
HWA RTU 1 SNI G 02/11/2020 - 09:00 02/11/2020 - 16:00 D SCA 1093431 Approved 07/05/2012 - 15:52
HWA RTU 1 SNI G 10/02/2021 - 09:00 10/02/2021 - 16:00 D SCA 1093874 Approved 07/05/2012 - 15:52
FHL RTU 1 SNI G 29/06/2021 - 08:00 29/06/2021 - 17:00 D RS 1095407 Approved 07/05/2012 - 15:52
FHL RTU 1 SNI G 18/03/2021 - 08:00 18/03/2021 - 17:00 D RS 1095404 Approved 07/05/2012 - 15:52
FHL RTU 1 SNI G 09/11/2020 - 09:30 09/11/2020 - 16:00 D RS 1095574 Approved 07/05/2012 - 15:52
LTN RTU 1 SNI G 07/10/2020 - 10:00 07/10/2020 - 16:00 D RS 1094614 Approved 07/05/2012 - 15:52
MGM RTU 1 SNI G 27/10/2020 - 09:30 27/10/2020 - 16:00 D RS 1095572 Approved 07/05/2012 - 15:52
MTN RTU 1 SNI G 18/11/2020 - 09:00 18/11/2020 - 16:00 D SCA 1093759 Approved 07/05/2012 - 15:52
MTR RTU 1 SNI G 03/11/2020 - 09:30 03/11/2020 - 16:00 D RS 1095573 Approved 07/05/2012 - 15:52
MTR RTU 1 SNI G 26/01/2021 - 08:00 26/01/2021 - 16:00 D RS 1095930 Approved 07/05/2012 - 15:52
MLG RTU 1 SNI G 28/10/2020 - 07:00 28/10/2020 - 17:00 D RS 1087004 Approved 07/05/2012 - 15:52
MLG RTU 1 SNI G 21/09/2020 - 08:00 21/09/2020 - 16:00 D RS 1095615 Approved 07/05/2012 - 15:52
MLG RTU 1 SNI G 28/04/2021 - 08:00 28/04/2021 - 16:00 D RS 1093816 Approved 07/05/2012 - 15:52
MNI RTU 1 SNI G 04/11/2020 - 07:30 04/11/2020 - 16:00 D RS 1094802 Approved 07/05/2012 - 15:52
PRM RTU 1 SNI G 27/04/2021 - 08:00 29/04/2021 - 17:00 D RS 1095481 Approved 07/05/2012 - 15:52
PRM RTU 1 SNI G 20/04/2021 - 08:00 22/04/2021 - 17:00 D RS 1095480 Approved 07/05/2012 - 15:52
PRM RTU 1 SNI G 03/05/2021 - 08:00 07/05/2021 - 17:00 D RS 1095482 Approved 07/05/2012 - 15:52
PRM RTU 1 SNI G 10/05/2021 - 08:00 13/05/2021 - 17:00 D RS 1095485 Approved 07/05/2012 - 15:52
PRM RTU 1 SNI G 19/05/2021 - 08:00 19/05/2021 - 17:00 D RS 1095486 Approved 07/05/2012 - 15:52
RDF RTU 1 SNI G 30/06/2021 - 08:00 30/06/2021 - 17:00 D RS 1095409 Approved 07/05/2012 - 15:52
RDF RTU 1 SNI G 16/03/2021 - 08:00 16/03/2021 - 17:00 D RS 1095405 Approved 07/05/2012 - 15:52
TNG RTU 1 SNI G 25/09/2020 - 12:00 25/09/2020 - 16:00 D RS 1096524 Approved 07/05/2012 - 15:52
TUI RTU 1 SNI G 17/03/2021 - 07:00 17/03/2021 - 17:00 D RS 1084175 Approved 07/05/2012 - 15:52
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.