Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
HAM 220CBF NNI G 07/12/2020 - 08:30 07/12/2020 - 12:30 D RS 1078687 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 02/11/2020 - 07:30 06/11/2020 - 18:00 C OPE 1085700 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 20/06/2020 - 07:00 20/06/2020 - 18:30 D OPE 1092341 Approved 07/05/2012 - 15:50
HAM CB 118 NNI G 27/02/2021 - 07:30 28/02/2021 - 18:00 D RS 1085521 Approved 07/05/2012 - 15:50
WAI T5 NNI G 15/11/2020 - 07:30 15/11/2020 - 18:00 D RS 1085914 Approved 07/05/2012 - 15:50
TWH FDR 2782 NNI L 07/10/2020 - 07:30 08/10/2020 - 18:00 D RS 1085905 Approved 07/05/2012 - 15:50
TWH FDR 2762 NNI L 07/10/2020 - 07:30 08/10/2020 - 18:00 D RS 1085904 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 25/01/2021 - 07:30 30/01/2021 - 18:30 C OPE 1084801 Approved 07/05/2012 - 15:50
TWH FDR 2742 NNI L 07/10/2020 - 07:30 08/10/2020 - 18:00 D RS 1085903 Approved 07/05/2012 - 15:50
TWH 33BS A NNI L 07/10/2020 - 07:30 08/10/2020 - 18:00 D RS 1088002 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 22/02/2021 - 07:30 27/02/2021 - 18:30 C OPE 1084802 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 15/02/2021 - 07:30 20/02/2021 - 18:30 C OPE 1084792 Approved 07/05/2012 - 15:50
TWH 33BS A NNI L 30/11/2020 - 07:00 04/12/2020 - 18:00 C RS 1089725 Approved 07/05/2012 - 15:50
TWH 33BS B NNI L 07/12/2020 - 07:00 11/12/2020 - 18:00 C RS 1089727 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 18/01/2021 - 07:30 23/01/2021 - 18:30 C OPE 1084786 Approved 07/05/2012 - 15:50
TWH 33BS B NNI L 12/10/2020 - 07:30 13/10/2020 - 18:00 D RS 1088004 Approved 07/05/2012 - 15:50
TWH CB 2808 NNI L 07/10/2020 - 07:30 08/10/2020 - 18:00 D RS 1088003 Approved 07/05/2012 - 15:50
HAM 220CBF NNI G 22/07/2020 - 12:00 22/07/2020 - 16:30 D RS 1082959 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 09/11/2020 - 07:00 13/11/2020 - 18:00 D OPE 1085701 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 16/10/2020 - 18:00 19/10/2020 - 07:30 C OPE 1087018 Approved 07/05/2012 - 15:50
TWH CB 2808 NNI L 12/10/2020 - 07:30 13/10/2020 - 18:00 D RS 1088005 Approved 07/05/2012 - 15:50
TWH T2 NNI G 12/10/2020 - 07:30 13/10/2020 - 18:00 D RS 1088298 Approved 07/05/2012 - 15:50
MPE CB 252 NNI G 14/03/2022 - 07:30 18/03/2022 - 18:30 C OPE 1085176 Approved 07/05/2012 - 15:50
TWH T1 NNI G 07/10/2020 - 07:30 08/10/2020 - 18:00 D RS 1088297 Approved 07/05/2012 - 15:50
TWH RTU 1 NNI G 25/11/2020 - 08:00 25/11/2020 - 18:00 D RS 1089726 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.