Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
ROT TRK 2 NNI G 16/08/2021 - 07:30 18/08/2021 - 16:30 D RS 1100216 Cancelled 07/05/2012 - 15:49
ROT WHE 1 NNI G 11/10/2021 - 07:30 15/10/2021 - 18:30 C RS 1092958 Approved 07/05/2012 - 15:49
TAK T5 NNI G 04/10/2021 - 07:30 09/10/2021 - 18:30 C RS 1085157 Approved 07/05/2012 - 15:49
TAK T5 NNI G 01/11/2021 - 07:30 06/11/2021 - 18:30 C RS 1085159 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 26/07/2021 - 07:00 29/07/2021 - 17:30 D RS 1104181 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 19/07/2021 - 07:00 22/07/2021 - 17:30 D RS 1104172 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 16/08/2021 - 07:00 18/08/2021 - 17:30 D RS 1104197 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 05/07/2021 - 07:00 07/07/2021 - 17:30 D RS 1104160 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 12/07/2021 - 07:00 14/07/2021 - 17:30 D RS 1104164 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 28/06/2021 - 07:00 30/06/2021 - 12:00 D RS 1104156 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 23/06/2021 - 07:30 23/06/2021 - 16:00 D RS 1097726 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 22/06/2021 - 07:30 22/06/2021 - 16:00 D RS 1096415 Approved 07/05/2012 - 15:49
WPA RTU 1 NNI G 01/02/2022 - 07:30 02/02/2022 - 19:30 C RS 1102781 Approved 07/05/2012 - 15:49
MTI RTU 1 NNI G 03/08/2021 - 08:00 03/08/2021 - 16:00 D RS 1104543 Approved 07/05/2012 - 15:49
BOB 227 247 267 NNI G 13/11/2021 - 07:30 13/11/2021 - 16:30 D RS 1097024 Approved 07/05/2012 - 15:49
HEN 220BZ A1 NNI G 26/08/2021 - 07:00 26/08/2021 - 18:00 D RS 1100245 Approved 07/05/2012 - 15:49
HEN 220BZ A1 NNI G 09/09/2021 - 07:00 10/09/2021 - 18:00 D RS 1100290 Approved 07/05/2012 - 15:49
HEN 220BZ A2 NNI G 09/09/2021 - 07:00 10/09/2021 - 18:00 D RS 1100291 Approved 07/05/2012 - 15:49
HEN 220BZ A2 NNI G 26/08/2021 - 07:00 26/08/2021 - 18:00 D RS 1100246 Approved 07/05/2012 - 15:49
KAW 11BZ A NNI L 10/08/2021 - 08:00 10/08/2021 - 16:00 D RS 1100198 Approved 07/05/2012 - 15:49
KAW 11BZ A NNI L 12/06/2023 - 08:00 12/06/2023 - 10:00 D RS 1096679 Approved 07/05/2012 - 15:49
KAW 11BZ A NNI L 14/06/2023 - 08:00 14/06/2023 - 10:00 D RS 1096682 Approved 07/05/2012 - 15:49
KAW 11BZ B NNI L 14/06/2023 - 10:00 14/06/2023 - 12:00 D RS 1096683 Approved 07/05/2012 - 15:49
KAW MAT 2 NNI G 10/08/2021 - 07:30 10/08/2021 - 18:30 D RS 1100190 Approved 07/05/2012 - 15:49
KAW MAT 1 NNI G 02/11/2021 - 07:30 02/11/2021 - 18:30 D RS 1100525 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.