Outage planning results

Last updated: Tue, 19/10/2021 - 12:10
Your current search

Sites: all sites selected

Outages search found 3635 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
HLY OTA 2 NNI G 23/03/2022 - 07:00 25/03/2022 - 18:00 D RS 1101201 Approved 07/05/2012 - 15:49
KOE MPE 1 PROT2 NNI G 22/02/2022 - 10:00 22/02/2022 - 14:00 D RS 1106619 Approved 13/08/2020 - 16:21
HLY OTA 2 NNI G 13/12/2021 - 07:30 18/12/2021 - 18:30 C RS 1085166 Approved 07/05/2012 - 15:49
BRB MDN 1 NNI G 16/03/2022 - 07:30 17/03/2022 - 18:30 D RS 1101166 Approved 07/05/2012 - 15:49
HLY OTA 2 NNI G 07/03/2022 - 08:00 10/03/2022 - 18:30 C RS 1097038 Approved 07/05/2012 - 15:49
BRB MDN 1 NNI G 27/04/2022 - 07:00 29/04/2022 - 18:00 C RS 1101320 Approved 07/05/2012 - 15:49
HTI FDR 222 NNI L 22/11/2021 - 07:30 24/11/2021 - 18:00 C RS 1097185 Approved 07/05/2012 - 15:49
KAW CB 2818 NNI L 08/02/2022 - 08:00 08/02/2022 - 18:00 D RS 1100931 Approved 19/09/2017 - 11:23
ARI CB 48 NNI G 02/02/2022 - 07:00 04/02/2022 - 18:00 D CLO 1102306 Approved 07/05/2012 - 15:49
TMU RTU 1 NNI G 10/11/2021 - 07:30 10/11/2021 - 18:00 D RS 1108024 Cancelled 07/05/2012 - 15:49
BOB T3 NNI G 23/11/2022 - 07:30 23/11/2022 - 16:30 D RS 1097029 Approved 07/05/2012 - 15:49
BOB T2 NNI G 23/11/2022 - 07:30 23/11/2022 - 16:30 D RS 1097026 Approved 07/05/2012 - 15:49
KIN T5 NNI G 14/02/2022 - 07:30 20/02/2022 - 18:30 C RS 1105929 Approved 07/05/2012 - 15:49
WKO T2 NNI G 02/05/2022 - 07:00 06/05/2022 - 18:30 C RS 1100267 Approved 07/05/2012 - 15:49
BOB T2 NNI G 30/04/2022 - 08:00 02/05/2022 - 16:00 D RS 1101329 Approved 07/05/2012 - 15:49
BOB OTA 2 NNI G 10/03/2022 - 07:30 11/03/2022 - 18:30 D RS 1101135 Approved 07/05/2012 - 15:49
MTO T2 NNI G 21/02/2022 - 07:30 25/02/2022 - 18:30 C RS 1101026 Approved 07/05/2012 - 15:49
HLY CB 602 NNI G 02/11/2021 - 07:30 02/11/2021 - 18:30 D RS 1100522 Cancelled 07/05/2012 - 15:49
MTO T2 NNI G 15/11/2021 - 07:30 18/11/2021 - 18:30 C RS 1100571 Approved 07/05/2012 - 15:49
KAW VT 107 NNI G 14/04/2022 - 08:00 14/04/2022 - 12:00 D RS 1106437 Approved 07/05/2012 - 15:49
HIN RTU 1 NNI G 13/04/2022 - 07:30 13/04/2022 - 12:00 D RS 1109807 Approved 07/05/2012 - 15:49
BOB OTA 2 NNI G 30/04/2022 - 08:00 02/05/2022 - 16:00 D RS 1101328 Approved 07/05/2012 - 15:49
BOB OTA 1 NNI G 27/10/2021 - 08:00 27/10/2021 - 17:00 D RS 1107274 Cancelled 07/05/2012 - 15:49
HEP FDR 2232 NNI L 28/10/2021 - 07:00 28/10/2021 - 12:00 D RS 1104976 Approved 17/11/2015 - 09:59
BOB OTA 1 NNI G 08/03/2022 - 07:30 09/03/2022 - 18:30 D RS 1101107 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.