Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
TMU T2 NNI G 23/11/2023 - 07:30 01/12/2023 - 18:30 C RS 1100580 Approved 07/05/2012 - 15:49
OTA 220CBF NNI G 21/11/2022 - 08:30 21/11/2022 - 18:30 D RS 1117752 Approved 07/05/2012 - 15:49
ARI 67 97 215 NNI G 21/01/2023 - 07:30 23/01/2023 - 12:30 C RS 1113087 Approved 07/05/2012 - 15:49
TMU T1 NNI G 13/11/2023 - 07:30 21/11/2023 - 18:30 C RS 1100494 Approved 07/05/2012 - 15:49
TAK T8 NNI G 22/08/2022 - 07:30 02/09/2022 - 18:00 C RS 1111020 Approved 07/05/2012 - 15:49
ROT T2 NNI G 15/11/2022 - 07:30 16/11/2022 - 18:30 D RS 1113131 Approved 07/05/2012 - 15:49
PEN T8 NNI G 16/01/2023 - 07:00 19/01/2023 - 18:00 C RS 1115913 Approved 07/05/2012 - 15:49
PEN T10 NNI G 17/10/2022 - 07:30 21/10/2022 - 18:30 C OPE 1113086 Approved 07/05/2012 - 15:49
KAW VT 47 NNI G 05/12/2022 - 07:30 06/12/2022 - 18:30 C RS 1113180 Approved 07/05/2012 - 15:49
OHK RTU 1 NNI G 11/10/2022 - 13:00 11/10/2022 - 15:00 D RS 1117891 Approved 07/05/2012 - 15:49
TMU T1 NNI G 28/11/2022 - 07:00 02/12/2022 - 16:00 C RS 1115491 Approved 07/05/2012 - 15:49
LFD T2 NNI L 20/02/2023 - 07:30 24/02/2023 - 18:30 C RS 1113321 Approved 07/05/2012 - 15:49
MTO T2 NNI G 13/02/2023 - 07:30 17/02/2023 - 18:30 C RS 1113305 Cancelled 07/05/2012 - 15:49
TMU FDR 24 NNI L 28/11/2022 - 07:00 02/12/2022 - 16:00 C RS 1114741 Approved 07/05/2012 - 15:49
TAK T8 NNI G 14/11/2022 - 07:30 18/11/2022 - 18:30 C RS 1113126 Approved 07/05/2012 - 15:49
MTO T2 NNI G 13/03/2023 - 07:00 19/03/2023 - 18:30 C RS 1103168 Approved 07/05/2012 - 15:49
MTO T2 NNI G 20/02/2023 - 07:00 24/02/2023 - 18:30 C RS 1103165 Approved 07/05/2012 - 15:49
TMU FDR 23 NNI L 14/03/2022 - 07:00 14/11/2022 - 16:00 C RS 1114740 Released 07/05/2012 - 15:49
MTO T2 NNI G 12/12/2022 - 07:30 12/12/2022 - 18:30 D RS 1119085 Approved 07/05/2012 - 15:49
MTO T1 NNI G 13/12/2022 - 07:30 13/12/2022 - 18:30 D RS 1119089 Approved 07/05/2012 - 15:49
TMU FDR 22 NNI L 28/11/2022 - 07:00 02/12/2022 - 16:00 C RS 1114739 Approved 07/05/2012 - 15:49
TAK T5 NNI G 25/10/2022 - 07:30 28/10/2022 - 18:30 C RS 1112936 Approved 07/05/2012 - 15:49
ROT T2 NNI G 22/08/2022 - 08:00 22/08/2022 - 16:00 D RS 1118068 Approved 07/05/2012 - 15:49
BOB FDR 272 NNI L 12/09/2022 - 08:00 12/09/2022 - 16:00 D RS 1119100 Approved 07/05/2012 - 15:49
MTO T1 NNI G 06/03/2023 - 07:00 12/03/2023 - 18:30 C RS 1103162 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.