Outage planning results

Last updated: Thu, 27/02/2020 - 02:40
Your current search

Sites: all sites selected

Outages search found 3132 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
PEN T6 NNI G 14/03/2020 - 07:00 15/03/2020 - 16:00 C RS 1085343 Approved 07/05/2012 - 15:50
ROS FDR 2112 NNI L 10/03/2020 - 07:00 10/03/2020 - 18:00 D RS 1088018 Approved 07/05/2012 - 15:50
KMO 167 177 204 NNI G 23/04/2020 - 07:30 24/04/2020 - 18:30 C RS 1070459 Approved 07/05/2012 - 15:50
OTA TIE 4 NNI G 08/05/2020 - 07:00 21/05/2020 - 16:00 C RS 1083869 Approved 07/05/2012 - 15:50
OTA 220BZ 2 NNI G 21/04/2020 - 07:30 21/04/2020 - 18:00 D RS 1086868 Approved 07/05/2012 - 15:50
OTA 220BZ 2 NNI G 30/03/2020 - 07:30 30/03/2020 - 18:00 D RS 1086856 Approved 07/05/2012 - 15:50
OTA C 30 NNI G 07/05/2020 - 07:30 07/05/2020 - 18:30 D RS 1070525 Approved 07/05/2012 - 15:50
KPO DIS 44 NNI G 11/08/2020 - 07:30 11/08/2020 - 18:00 D RS 1082110 Approved 16/06/2015 - 09:16
MPE 110BZ NNI G 28/04/2020 - 10:00 28/04/2020 - 12:00 D RS 1084696 Approved 18/12/2012 - 13:40
DRY GLN 1 NNI G 28/04/2020 - 07:00 01/05/2020 - 18:00 C RS 1084665 Approved 07/05/2012 - 15:50
DRY GLN 1 NNI G 02/04/2020 - 07:00 02/04/2020 - 18:00 D RS 1070432 Approved 07/05/2012 - 15:50
DRY HLY 1 NNI G 23/05/2020 - 06:30 24/05/2020 - 19:30 C RS 1084195 Approved 07/05/2012 - 15:50
DRY OTA 1 NNI G 23/06/2020 - 06:30 28/06/2020 - 19:30 C RS 1084197 Approved 07/05/2012 - 15:50
DRY OTA 1 NNI G 01/11/2021 - 07:30 06/11/2021 - 18:30 C RS 1085158 Approved 07/05/2012 - 15:50
DRY OTA 1 NNI G 04/10/2021 - 07:30 09/10/2021 - 18:30 C RS 1085156 Approved 07/05/2012 - 15:50
DRY OTA 1 NNI G 06/12/2021 - 07:30 11/12/2021 - 18:30 C RS 1085160 Approved 07/05/2012 - 15:50
KMO MTM 1 NNI G 22/04/2020 - 07:30 26/04/2020 - 18:30 C RS 1070462 Approved 07/05/2012 - 15:50
DRY GLN 2 NNI G 31/03/2020 - 07:00 31/03/2020 - 18:00 D RS 1070422 Approved 07/05/2012 - 15:50
WIR 2176B NNI L 27/02/2020 - 08:30 27/02/2020 - 16:00 D RS 1089813 Approved 07/05/2012 - 15:50
PEN T5 NNI G 15/03/2020 - 07:30 15/03/2020 - 16:00 D RS 1085342 Approved 07/05/2012 - 15:50
PEN T5 NNI G 22/03/2020 - 07:30 22/03/2020 - 17:00 D RS 1085351 Approved 07/05/2012 - 15:50
OTA TIE 5 NNI G 30/03/2020 - 07:30 30/03/2020 - 18:00 D RS 1086858 Approved 07/05/2012 - 15:50
OTA TIE 5 NNI G 03/06/2020 - 07:00 11/06/2020 - 16:00 C RS 1084272 Approved 07/05/2012 - 15:50
BOB C 11 NNI G 09/05/2020 - 07:00 11/05/2020 - 19:00 C RS 1070324 Approved 07/05/2012 - 15:50
KPO CB 252 NNI G 03/05/2021 - 07:30 08/06/2021 - 18:00 C RS 1088393 Approved 12/11/2019 - 09:46
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.