Outage planning results

Last updated: Thu, 27/02/2020 - 02:40
Your current search

Sites: all sites selected

Outages search found 3132 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
OTA 220CBF 1 NNI G 31/03/2020 - 07:30 31/03/2020 - 18:00 D RS 1086860 Approved 07/05/2012 - 15:50
OTA 220CBF 1 NNI G 22/04/2020 - 07:30 22/04/2020 - 18:00 D RS 1086872 Approved 07/05/2012 - 15:50
OTA 220CBF 2 NNI G 21/04/2020 - 07:30 21/04/2020 - 18:00 D RS 1086869 Approved 07/05/2012 - 15:50
OTA 220CBF 2 NNI G 30/03/2020 - 07:30 30/03/2020 - 18:00 D RS 1086857 Approved 07/05/2012 - 15:50
PAK WKM 1 NNI G 23/03/2020 - 07:30 25/03/2020 - 18:30 D RS 1070411 Approved 07/05/2012 - 15:50
PAK WKM 2 NNI G 18/03/2020 - 07:30 20/03/2020 - 18:30 D RS 1070403 Approved 07/05/2012 - 15:50
WKM TIE 1 NNI G 11/05/2020 - 07:30 12/05/2020 - 18:30 C RS 1070503 Approved 07/05/2012 - 15:50
WKM TIE 2 NNI G 13/05/2020 - 07:30 14/05/2020 - 18:30 C RS 1070510 Approved 07/05/2012 - 15:50
PEN T7 NNI G 22/03/2020 - 07:30 22/03/2020 - 17:00 D RS 1085353 Approved 07/05/2012 - 15:50
PEN T7 NNI G 15/03/2020 - 07:30 15/03/2020 - 16:00 D RS 1085344 Approved 07/05/2012 - 15:50
WKM 220BS E NNI G 18/03/2020 - 07:30 20/03/2020 - 18:30 D RS 1074066 Approved 07/05/2012 - 15:50
WKM 220BS E NNI G 23/03/2020 - 07:30 25/03/2020 - 18:30 D RS 1074068 Approved 07/05/2012 - 15:50
WKM 220BS E NNI G 13/05/2020 - 07:30 14/05/2020 - 18:30 C RS 1070511 Approved 07/05/2012 - 15:50
WKM 220BS F NNI G 11/05/2020 - 07:30 12/05/2020 - 18:30 C RS 1074069 Approved 07/05/2012 - 15:50
OHW WKM 1 NNI G 23/04/2020 - 08:00 23/04/2020 - 18:00 D RS 1083931 Approved 07/05/2012 - 15:50
MPE FDR 302 NNI L 16/03/2020 - 08:30 27/03/2020 - 15:00 C RS 1088779 Approved 09/04/2013 - 08:50
OHW CB 212 NNI G 05/10/2020 - 07:00 08/10/2020 - 18:00 C RS 1073839 Approved 07/05/2012 - 15:50
GLN CB 2542 NNI L 11/06/2020 - 07:00 11/06/2020 - 17:00 D RS 1070484 Approved 02/07/2018 - 10:45
KIN T6 NNI G 02/06/2020 - 07:00 16/06/2020 - 17:00 C RS 1089848 Approved 18/01/2019 - 16:03
OHW RTU 1 NNI G 29/10/2020 - 09:00 29/10/2020 - 16:00 D RS 1089789 Approved 07/05/2012 - 15:50
OHW RTU 1 NNI G 23/09/2020 - 08:00 23/09/2020 - 16:00 D RS 1073828 Approved 07/05/2012 - 15:50
KPO DIS 64 NNI G 13/06/2021 - 07:30 13/06/2021 - 18:00 D RS 1088403 Approved 16/06/2015 - 09:17
KIN 11BS D NNI L 04/03/2020 - 07:30 04/03/2020 - 17:00 D RS 1085268 Approved 17/05/2018 - 10:43
KIN T9 NNI G 29/04/2020 - 07:00 13/05/2020 - 17:00 C RS 1089528 Approved 09/10/2018 - 10:25
ATI TRK 1 NNI G 16/06/2020 - 07:30 19/06/2020 - 18:30 C RS 1087881 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.