Outage planning results

Last updated: Tue, 15/10/2019 - 18:40
Your current search

Sites: all sites selected

Outages search found 4038 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
GLN CB 2542 NNI L 11/06/2020 - 07:00 11/06/2020 - 17:00 D RS 1070484 Approved 02/07/2018 - 10:45
KIN T9 NNI G 03/11/2019 - 02:00 17/11/2019 - 02:00 C RS 1083324 Approved 09/10/2018 - 10:25
KIN CB 2072 NNI L 03/11/2019 - 02:00 21/11/2019 - 17:00 C RS 1083317 Approved 09/10/2018 - 10:30
CCT 9999 MISC NNI NNI G 07/11/2019 - 12:00 07/11/2019 - 18:00 D RS 1084473 Approved 23/08/2017 - 10:34
HEP FDR 2342 NNI L 25/10/2019 - 07:30 06/11/2019 - 11:45 C RS 1084331 Approved 17/11/2015 - 10:00
MDN STC 6 HVDC G 10/02/2020 - 07:30 14/02/2020 - 18:30 C RS 1070286 Approved 04/07/2013 - 15:07
HEP 33BZ NNI L 24/03/2020 - 09:00 24/03/2020 - 16:00 D RS 1083289 Approved 17/11/2015 - 10:02
TRK 11BS B NNI L 07/03/2020 - 07:30 08/03/2020 - 18:30 C RS 1072864 Approved 07/05/2012 - 15:50
PEN RTU 2 NNI G 05/02/2020 - 08:30 05/02/2020 - 18:30 D SCA 1083189 Approved 20/05/2013 - 15:20
MDN STC 5 HVDC G 24/02/2020 - 07:30 28/02/2020 - 18:30 C RS 1070297 Approved 04/07/2013 - 15:03
PEN RTU 2 NNI G 22/01/2020 - 08:30 22/01/2020 - 18:30 D SCA 1083185 Approved 20/05/2013 - 15:20
ROS 22BZ A NNI L 23/10/2019 - 07:30 23/10/2019 - 18:00 D RS 1080334 Approved 23/03/2018 - 10:03
ROS 22BZ B NNI L 23/10/2019 - 07:30 23/10/2019 - 18:00 D RS 1080336 Approved 23/03/2018 - 10:04
PEN RTU 2 NNI G 29/01/2020 - 08:30 29/01/2020 - 18:30 D SCA 1083187 Approved 20/05/2013 - 15:20
ROS 22BZ K NNI L 23/10/2019 - 07:30 23/10/2019 - 18:00 D RS 1080337 Approved 23/03/2018 - 10:04
PEN RTU 2 NNI G 04/12/2019 - 08:30 04/12/2019 - 18:30 D SCA 1083183 Approved 20/05/2013 - 15:20
ROS 22AFD NNI L 22/10/2019 - 07:30 22/10/2019 - 18:00 D RS 1080328 Approved 23/03/2018 - 10:08
ALB SVL GXP TIE NNI G 31/10/2019 - 09:00 31/10/2019 - 11:30 D OTH 1083480 Approved 12/04/2018 - 09:50
ROT 110CBF NNI G 11/02/2020 - 08:00 11/02/2020 - 17:00 D RS 1083914 Approved 11/12/2018 - 15:09
ROT 110CBF NNI G 20/03/2020 - 08:00 27/03/2020 - 17:00 D RS 1080538 Approved 11/12/2018 - 15:09
ROT 110CBF NNI G 16/02/2020 - 08:00 16/02/2020 - 17:00 D RS 1083920 Approved 11/12/2018 - 15:09
PEN RTU 2 NNI G 17/10/2019 - 08:30 18/10/2019 - 18:30 D SCA 1083173 Approved 20/05/2013 - 15:20
PEN RTU 2 NNI G 07/11/2019 - 08:30 07/11/2019 - 18:30 D SCA 1083175 Approved 20/05/2013 - 15:20
WAI AUFLS NNI G 06/04/2020 - 07:30 06/04/2020 - 18:30 D RS 1070439 Approved 07/05/2012 - 15:50
HEP 110BZ A NNI G 19/03/2020 - 07:30 19/03/2020 - 17:30 D RS 1074368 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.