Outage planning results

Last updated: Mon, 18/10/2021 - 18:40
Your current search

Sites: all sites selected

Outages search found 3668 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BLN 33BS C SI L 29/11/2021 - 07:30 29/11/2021 - 18:30 D RS 1107847 Approved 07/05/2012 - 15:52
BLN CB 2228 SI L 29/11/2021 - 07:30 29/11/2021 - 18:30 D RS 1107849 Approved 07/05/2012 - 15:52
HKK C7C8C9 SI G 12/11/2021 - 08:00 12/11/2021 - 16:00 D RS 1106787 Approved 07/05/2012 - 15:52
BEN 220BS CHANGE SI G 05/11/2021 - 15:30 05/11/2021 - 16:00 D PSO 1109752 Approved 07/05/2012 - 15:52
BLN CB 2028 CBL SI L 29/11/2021 - 07:30 29/11/2021 - 18:30 D RS 1107848 Approved 07/05/2012 - 15:52
BEN 220BS CHANGE SI G 27/10/2021 - 07:00 27/10/2021 - 07:30 D PSO 1109751 Approved 07/05/2012 - 15:52
FKN FDR 2772 SI L 01/03/2022 - 07:30 03/03/2022 - 18:30 C RS 1106828 Approved 07/05/2012 - 15:52
DOB T11 SI G 28/03/2022 - 07:30 01/04/2022 - 18:30 C RS 1101336 Approved 07/05/2012 - 15:52
DOB T11 SI G 03/12/2021 - 07:30 03/12/2021 - 18:30 D RS 1108284 Approved 07/05/2012 - 15:52
DOB T11 SI G 24/01/2022 - 07:30 29/01/2022 - 18:30 C RS 1104537 Approved 07/05/2012 - 15:52
HOR AUVLS SI G 07/03/2022 - 07:30 17/03/2022 - 18:30 C RS 1103246 Approved 07/05/2012 - 15:52
ARA WRK 1 SNI G 26/11/2021 - 07:30 27/11/2021 - 17:30 C RS 1100640 Approved 07/05/2012 - 15:52
CUL T22 SI G 21/03/2022 - 07:30 25/03/2022 - 17:00 C RS 1109969 Approved 07/05/2012 - 15:52
ARI HTI ONG 1 SNI G 21/03/2022 - 07:30 26/03/2022 - 18:30 C RS 1108542 Approved 07/05/2012 - 15:52
ARI HTI ONG 1 SNI G 26/10/2021 - 07:00 26/10/2021 - 18:30 D RS 1100411 Approved 07/05/2012 - 15:52
ARI HTI ONG 1 SNI G 10/01/2022 - 07:00 12/01/2022 - 18:00 C RS 1107356 Approved 07/05/2012 - 15:52
ARI HTI ONG 1 SNI G 14/12/2021 - 07:30 15/12/2021 - 18:30 C RS 1108929 Approved 07/05/2012 - 15:52
BPE BRK 1 SNI G 15/11/2021 - 07:00 19/11/2021 - 17:30 C RS 1100566 Approved 07/05/2012 - 15:52
BPE BRK 1 SNI G 08/11/2021 - 07:00 12/11/2021 - 17:30 C RS 1100539 Approved 07/05/2012 - 15:52
BPE BRK 2 SNI G 22/11/2021 - 06:30 26/11/2021 - 17:30 C RS 1100605 Approved 07/05/2012 - 15:52
BPE BRK 2 SNI G 29/11/2021 - 06:30 03/12/2021 - 17:30 C RS 1100642 Approved 07/05/2012 - 15:52
BPE BRK 2 SNI G 02/04/2022 - 07:00 02/04/2022 - 18:00 D RS 1106919 Approved 07/05/2012 - 15:52
BPE BRK 2 SNI G 19/04/2022 - 07:00 22/04/2022 - 18:30 D RS 1108739 Approved 07/05/2012 - 15:52
BPE MHO 1 SNI G 21/02/2022 - 07:30 26/02/2022 - 17:00 C RS 1106015 Approved 07/05/2012 - 15:52
BPE WDV 2 SNI G 26/10/2021 - 07:30 28/10/2021 - 18:30 C RS 1100429 Approved 07/05/2012 - 15:52
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.