Outage planning results

Last updated: Tue, 20/10/2020 - 22:40
Your current search

Sites: all sites selected

Outages search found 3657 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
PEN T10 NNI G 12/11/2020 - 07:00 14/11/2020 - 19:00 C OPE 1096976 Approved 07/05/2012 - 15:49
PEN T9 NNI G 16/11/2020 - 07:00 24/11/2020 - 18:00 C RS 1095610 Approved 07/05/2012 - 15:49
PEN C 1 NNI G 15/01/2021 - 07:00 17/01/2021 - 19:00 C RS 1094103 Approved 07/05/2012 - 15:49
PEN T10 NNI G 09/11/2020 - 06:30 11/11/2020 - 19:00 C OPE 1096828 Approved 07/05/2012 - 15:49
PEN T8 NNI G 02/11/2020 - 08:00 10/11/2020 - 18:30 C RS 1095609 Approved 07/05/2012 - 15:49
PEN T8 NNI G 15/01/2021 - 07:00 17/01/2021 - 19:00 C RS 1094107 Approved 07/05/2012 - 15:49
OTA PEN 2 NNI G 29/10/2020 - 07:00 30/10/2020 - 19:00 C RS 1085778 Approved 07/05/2012 - 15:49
OWH T2 NNI G 30/08/2021 - 07:30 03/09/2021 - 18:30 C RS 1095857 Approved 07/05/2012 - 15:49
OTA PEN 2 NNI G 09/02/2021 - 07:30 23/03/2021 - 18:30 C RS 1096748 Approved 07/05/2012 - 15:49
PEN T10 NNI G 03/05/2021 - 07:30 07/05/2021 - 18:30 C OPE 1092825 Approved 07/05/2012 - 15:49
OTA PEN 5 NNI G 09/11/2020 - 06:30 11/11/2020 - 19:00 C RS 1085779 Approved 07/05/2012 - 15:49
OTA ROS 2 NNI G 23/11/2020 - 07:00 24/11/2020 - 18:30 C RS 1094528 Approved 07/05/2012 - 15:49
OTA SWN 1 NNI G 08/12/2020 - 07:30 10/12/2020 - 18:30 C RS 1094607 Approved 07/05/2012 - 15:49
OTA PEN 5 NNI G 18/01/2021 - 07:00 22/01/2021 - 19:00 C RS 1094119 Approved 07/05/2012 - 15:49
OTA PEN 6 NNI G 15/01/2021 - 07:00 17/01/2021 - 19:00 C RS 1094099 Approved 07/05/2012 - 15:49
OTA T3 NNI G 21/10/2020 - 07:00 22/10/2020 - 18:00 C RS 1094375 Approved 07/05/2012 - 15:49
OTA PEN 6 NNI G 12/11/2020 - 07:00 14/11/2020 - 19:00 C RS 1085780 Approved 07/05/2012 - 15:49
OTA C 12 NNI G 15/02/2021 - 07:00 16/02/2021 - 18:00 C RS 1085766 Approved 07/05/2012 - 15:49
OTA ROS 1 NNI G 23/11/2020 - 07:00 25/11/2020 - 19:00 C RS 1085781 Cancelled 07/05/2012 - 15:49
OTA WKM 2 NNI G 16/03/2021 - 07:00 18/03/2021 - 19:00 C RS 1089061 Approved 07/05/2012 - 15:49
OTA ROS 1 NNI G 16/03/2020 - 07:00 24/09/2021 - 16:00 C RS 1089181 Released 07/05/2012 - 15:49
PEN T10 NNI G 20/10/2020 - 12:30 23/10/2020 - 18:30 C OPE 1094787 Released 07/05/2012 - 15:49
OWH T1 NNI G 02/08/2021 - 07:30 06/08/2021 - 18:30 C RS 1095856 Approved 07/05/2012 - 15:49
OTA ROS 2 NNI G 26/11/2020 - 07:00 28/11/2020 - 19:00 C RS 1085782 Approved 07/05/2012 - 15:49
ROS FDR 62 NNI G 27/10/2020 - 07:30 07/11/2020 - 18:00 C RS 1097353 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.