Outage planning results

Last updated: Tue, 15/06/2021 - 16:40
Your current search

Sites: all sites selected

Outages search found 3563 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
HAY RTU 1 SNI G 23/02/2022 - 08:00 23/02/2022 - 16:00 D RS 1105033 Approved 07/05/2012 - 15:53
HOR RTU 1 SI G 21/06/2021 - 09:00 21/06/2021 - 11:00 D RS 1102657 Approved 07/05/2012 - 15:51
HOR RTU 1 SI G 06/09/2021 - 07:30 06/09/2021 - 18:30 D RS 1100276 Approved 07/05/2012 - 15:51
HOR RTU 1 SI G 02/02/2022 - 07:30 02/02/2022 - 18:30 D RS 1103241 Approved 07/05/2012 - 15:51
HOR RTU 1 SI G 26/01/2022 - 07:30 26/01/2022 - 18:30 D RS 1103240 Approved 07/05/2012 - 15:51
HOR RTU 1 SI G 15/06/2022 - 07:30 15/06/2022 - 18:30 D RS 1103254 Approved 07/05/2012 - 15:51
HOR RTU 1 SI G 22/06/2022 - 07:30 22/06/2022 - 18:30 D RS 1103255 Approved 07/05/2012 - 15:51
HOR RTU 1 SI G 08/06/2022 - 07:30 08/06/2022 - 18:30 D RS 1101421 Approved 07/05/2012 - 15:51
HOR RTU 1 SI G 09/03/2022 - 07:30 09/03/2022 - 12:00 D RS 1103247 Approved 07/05/2012 - 15:51
HOR RTU 1 SI G 02/03/2022 - 07:30 02/03/2022 - 12:00 D RS 1103245 Approved 07/05/2012 - 15:51
HOR RTU 1 SI G 23/02/2022 - 07:30 23/02/2022 - 18:30 D RS 1103242 Approved 07/05/2012 - 15:51
HOR RTU 1 SI G 27/04/2022 - 07:30 27/04/2022 - 18:30 D RS 1103250 Approved 07/05/2012 - 15:51
HOR RTU 1 SI G 06/04/2022 - 07:30 06/04/2022 - 12:00 D RS 1103249 Approved 07/05/2012 - 15:51
HAY RTU 1 SNI G 08/12/2021 - 08:00 08/12/2021 - 16:00 D RS 1105031 Approved 07/05/2012 - 15:53
HAY RTU 1 SNI G 22/06/2021 - 08:00 22/06/2021 - 14:00 D RS 1105618 Approved 07/05/2012 - 15:53
CPK T12 SNI L 01/02/2022 - 07:30 01/02/2022 - 17:30 D RS 1100871 Approved 07/05/2012 - 15:53
CPK T12 SNI L 06/10/2021 - 07:00 07/10/2021 - 18:30 D RS 1104919 Approved 07/05/2012 - 15:53
CPK T12 SNI L 01/02/2022 - 07:30 01/02/2022 - 17:30 D RS 1098890 Cancelled 07/05/2012 - 15:53
CPK T11 SNI L 01/02/2022 - 07:30 01/02/2022 - 17:30 D RS 1098889 Cancelled 07/05/2012 - 15:53
CPK T11 SNI L 01/02/2022 - 07:30 01/02/2022 - 17:30 D RS 1100870 Approved 07/05/2012 - 15:53
MNG FDR 2032 NNI L 21/06/2021 - 07:30 21/06/2021 - 16:00 D RS 1105440 Approved 02/09/2019 - 11:02
WRK CB 2068 SNI L 16/05/2022 - 07:30 16/05/2022 - 17:00 D RS 1102683 Approved 07/05/2012 - 15:53
PTS 1389 BRK SFD SNI G 07/03/2022 - 08:30 07/03/2022 - 17:00 D RS 1101095 Approved 07/05/2012 - 15:53
PTS 1665 RPO WRK SNI G 25/06/2021 - 09:00 25/06/2021 - 17:00 D RS 1103326 Cancelled 07/05/2012 - 15:53
PTS 1667 RPO WRK SNI G 08/03/2022 - 07:30 08/03/2022 - 17:00 D RS 1101118 Approved 07/05/2012 - 15:53
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.