Outage planning results

Last updated: Fri, 17/09/2021 - 19:10
Your current search

Sites: all sites selected

Outages search found 3870 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
HEN FDR 2192 NNI L 29/10/2021 - 13:00 29/10/2021 - 18:00 D RS 1104999 Approved 16/06/2016 - 09:55
HEN FDR 2302 NNI L 29/10/2021 - 07:00 29/10/2021 - 12:00 D RS 1104994 Approved 16/06/2016 - 09:55
HEN FDR 2322 NNI L 29/10/2021 - 07:00 29/10/2021 - 12:00 D RS 1104993 Approved 16/06/2016 - 09:55
HEN FDR 2332 NNI L 29/10/2021 - 07:00 29/10/2021 - 12:00 D RS 1104992 Approved 16/06/2016 - 09:56
HEN FDR 2342 NNI L 29/10/2021 - 07:00 29/10/2021 - 12:00 D RS 1104991 Approved 16/06/2016 - 09:56
HEN FDR 2352 NNI L 29/10/2021 - 07:00 29/10/2021 - 12:00 D RS 1104990 Approved 16/06/2016 - 09:56
HEN CB 2188 NNI G 29/10/2021 - 07:00 29/10/2021 - 12:00 D RS 1104995 Approved 16/06/2016 - 10:13
HEN CB 2188 NNI G 29/10/2021 - 13:00 29/10/2021 - 18:00 D RS 1104998 Approved 16/06/2016 - 10:13
HAM C 2 NNI G 30/10/2021 - 07:30 30/10/2021 - 18:30 D RS 1107610 Approved 21/01/2020 - 14:36
WHU FDR 2232 NNI L 24/09/2021 - 06:30 24/09/2021 - 16:00 D RS 1109005 Approved 14/02/2020 - 14:21
KOE MPE 1 PROT2 NNI G 26/10/2021 - 10:00 26/10/2021 - 14:00 D RS 1106619 Approved 13/08/2020 - 16:21
KOE MPE 1 PROT2 NNI G 27/10/2021 - 10:00 27/10/2021 - 14:00 D RS 1106621 Approved 13/08/2020 - 16:21
KOE MPE 2 PROT2 NNI G 26/10/2021 - 14:00 26/10/2021 - 18:00 D RS 1106620 Approved 13/08/2020 - 16:21
KOE MPE 2 PROT2 NNI G 27/10/2021 - 14:00 27/10/2021 - 18:00 D RS 1106622 Approved 13/08/2020 - 16:21
MTI CB 98 NNI G 09/10/2021 - 07:00 09/10/2021 - 14:00 D RS 1108620 Approved 01/09/2020 - 11:10
MTI CB 98 NNI G 18/09/2021 - 07:00 18/09/2021 - 14:00 D RS 1108619 Approved 01/09/2020 - 11:10
GLN CB 2542 NNI L 02/03/2022 - 07:00 02/03/2022 - 18:00 D RS 1107423 Approved 02/07/2018 - 10:45
GLN CB 2542 NNI L 11/10/2021 - 07:00 11/10/2021 - 18:00 D RS 1107821 Approved 02/07/2018 - 10:45
GLN CB 2542 NNI L 13/10/2021 - 07:00 13/10/2021 - 18:00 D RS 1105211 Approved 02/07/2018 - 10:45
KIN T9 NNI G 18/01/2022 - 07:30 19/01/2022 - 18:30 D RS 1100827 Approved 09/10/2018 - 10:25
MTI CB 128 NNI G 18/09/2021 - 07:00 18/09/2021 - 14:00 D RS 1108591 Approved 14/01/2019 - 11:50
MTI CB 128 NNI G 09/10/2021 - 07:00 09/10/2021 - 14:00 D RS 1108599 Approved 14/01/2019 - 11:50
TAK FDR 2132 NNI L 10/08/2021 - 08:00 17/10/2021 - 16:00 D RS 1107317 Released 15/06/2017 - 09:59
TAK FDR 2152 NNI L 24/11/2021 - 08:00 24/11/2021 - 16:00 D RS 1100625 Approved 15/06/2017 - 09:59
TAK FDR 2192 NNI L 25/11/2021 - 08:00 25/11/2021 - 16:00 D RS 1100626 Approved 15/06/2017 - 10:00
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.