Outage planning results

Last updated: Fri, 27/05/2022 - 18:40
Your current search

Sites: all sites selected

Outages search found 3469 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
HEN MPE 1 NNI G 20/06/2022 - 09:00 21/06/2022 - 17:00 D RS 1115281 Approved 07/05/2012 - 15:49
HEN SWN 1 NNI G 12/07/2022 - 07:00 12/07/2022 - 15:30 D RS 1115358 Approved 07/05/2012 - 15:49
OWH 110CBF NNI G 28/09/2022 - 07:30 28/09/2022 - 17:00 D RS 1106709 Approved 29/05/2017 - 11:26
ARI HAM 2 NNI G 25/10/2022 - 08:00 28/10/2022 - 18:30 D RS 1113090 Approved 07/05/2012 - 15:49
HIN FDR 282 NNI L 29/05/2022 - 07:30 29/05/2022 - 16:30 D RS 1102163 Cancelled 07/05/2012 - 15:49
HIN KPO 1 NNI G 12/06/2022 - 07:30 12/06/2022 - 16:30 D RS 1101414 Approved 07/05/2012 - 15:49
TMI T2 NNI G 15/03/2023 - 07:30 15/03/2023 - 18:30 D RS 1114245 Approved 07/05/2012 - 15:50
HLY CB 262 NNI G 19/09/2022 - 07:00 21/09/2022 - 18:00 D RS 1113048 Approved 07/05/2012 - 15:49
TMU 11kV AFD B2 NNI L 14/06/2022 - 07:30 14/06/2022 - 17:00 D RS 1114910 Approved 03/03/2022 - 08:12
ARI HAM 2 NNI G 20/06/2022 - 07:00 20/06/2022 - 18:30 D RS 1101443 Approved 07/05/2012 - 15:49
ARI HTI 1 NNI G 25/10/2022 - 08:00 28/10/2022 - 18:30 D RS 1113091 Approved 07/05/2012 - 15:49
ARI KIN 1 NNI G 27/03/2023 - 07:00 27/03/2023 - 18:00 D RS 1113387 Approved 07/05/2012 - 15:49
ARI KIN 2 NNI G 03/10/2022 - 07:30 04/10/2022 - 18:30 D RS 1113073 Approved 07/05/2012 - 15:49
OWH 110CBF NNI G 19/09/2022 - 08:00 19/09/2022 - 17:00 D RS 1106707 Approved 29/05/2017 - 11:26
MPE CB 292 NNI G 24/11/2022 - 07:30 24/11/2022 - 18:30 D RS 1113163 Approved 07/05/2012 - 15:50
TMU 11CBF NNI L 04/08/2022 - 08:00 05/08/2022 - 18:00 D RS 1116320 Approved 07/05/2012 - 15:50
MPE CB 292 NNI G 11/08/2022 - 07:00 11/08/2022 - 18:00 D OPE 1116357 Approved 07/05/2012 - 15:50
HTI FDR 262 NNI L 25/04/2023 - 07:00 25/04/2023 - 18:00 D RS 1113473 Approved 07/05/2012 - 15:49
TMU 11CBF NNI L 16/06/2022 - 08:00 17/06/2022 - 18:00 D RS 1116330 Approved 07/05/2012 - 15:50
WHU 33kV AFD BUS K NNI L 15/06/2022 - 07:30 15/06/2022 - 17:00 D RS 1114911 Approved 03/03/2022 - 08:17
OWH 110CBF NNI G 13/09/2022 - 08:00 13/09/2022 - 17:30 D RS 1106702 Approved 29/05/2017 - 11:26
BOB FDR 102 NNI L 31/10/2022 - 07:00 31/10/2022 - 18:00 D RS 1113092 Approved 07/05/2012 - 15:49
BOB FDR 102 NNI L 30/05/2022 - 08:15 30/05/2022 - 08:30 D RS 1117003 Approved 07/05/2012 - 15:49
WHU RTU 1 NNI G 01/06/2022 - 10:30 01/06/2022 - 13:00 D RS 1111834 Approved 07/05/2012 - 15:49
WKO RTU 1 NNI G 01/06/2022 - 08:00 01/06/2022 - 10:00 D RS 1111833 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.