Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
ARI CB 48 NNI G 02/02/2022 - 07:00 04/02/2022 - 18:00 D CLO 1102306 Approved 07/05/2012 - 15:49
HIN T1 NNI G 21/12/2021 - 07:30 21/12/2021 - 18:30 D RS 1109380 Approved 07/05/2012 - 15:49
ALB HEN GXP TIE NNI G 26/11/2021 - 07:00 26/11/2021 - 18:30 D OTH 1109788 Approved 12/03/2018 - 13:08
HIN RTU 1 NNI G 13/04/2022 - 07:30 13/04/2022 - 12:00 D RS 1109807 Approved 07/05/2012 - 15:49
HEN HEP 1 NNI G 01/02/2022 - 07:30 01/02/2022 - 18:30 D RS 1109119 Approved 07/05/2012 - 15:49
CCT 8272 BWK SDN SI G 27/10/2021 - 10:00 27/10/2021 - 16:00 D RS 1109949 Approved 09/06/2021 - 08:31
KPO TMU 1 PROT2 NNI G 09/02/2022 - 14:00 09/02/2022 - 18:00 D RS 1106895 Approved 12/07/2021 - 14:29
HAY 11BZ AB HVDC H 30/04/2022 - 08:00 30/04/2022 - 17:00 D RS 1107974 Approved 05/11/2018 - 09:18
ARI HTI 1 PROT2 NNI G 12/02/2022 - 10:00 12/02/2022 - 14:00 D RS 1106894 Approved 12/07/2021 - 14:33
KAW VT 107 NNI G 14/04/2022 - 08:00 14/04/2022 - 12:00 D RS 1106437 Approved 07/05/2012 - 15:49
CST SFD 2 PROT2 SNI G 13/02/2022 - 14:00 13/02/2022 - 18:00 D RS 1106950 Approved 16/07/2021 - 13:54
HAY 11BZ AB HVDC H 20/04/2022 - 08:00 20/04/2022 - 17:00 D RS 1107969 Approved 05/11/2018 - 09:18
KAW T13 NNI G 12/11/2021 - 08:00 12/11/2021 - 18:00 D RS 1109670 Approved 07/05/2012 - 15:49
CST SFD 2 PROT2 SNI G 15/02/2022 - 16:30 15/02/2022 - 19:30 D RS 1106951 Approved 16/07/2021 - 13:54
KAW T7 NNI G 11/04/2022 - 08:00 11/04/2022 - 12:00 D RS 1106314 Approved 07/05/2012 - 15:49
KAW T7 NNI G 14/04/2022 - 08:00 14/04/2022 - 12:00 D RS 1106436 Approved 07/05/2012 - 15:49
HAY 11BZ AB HVDC H 03/02/2022 - 08:00 03/02/2022 - 17:00 D RS 1107932 Approved 05/11/2018 - 09:18
KAW T8 NNI G 15/02/2022 - 07:30 16/02/2022 - 18:30 D RS 1100966 Cancelled 07/05/2012 - 15:49
HAY 11BZ AB HVDC H 31/01/2022 - 08:00 31/01/2022 - 17:00 D RS 1107929 Approved 05/11/2018 - 09:18
TRK RTU 1 NNI G 27/11/2021 - 07:30 29/11/2021 - 18:30 D RS 1105292 Approved 07/05/2012 - 15:49
KOE MPE 1 NNI G 29/11/2021 - 07:00 30/11/2021 - 18:00 D RS 1100648 Approved 07/05/2012 - 15:49
MPE RTU 1 NNI G 04/11/2021 - 07:30 04/11/2021 - 18:30 D RS 1103596 Approved 07/05/2012 - 15:49
HAY 11BZ AB HVDC H 28/01/2022 - 08:00 28/01/2022 - 17:00 D RS 1107921 Approved 05/11/2018 - 09:18
KOE MPE 2 NNI G 01/12/2021 - 07:00 02/12/2021 - 18:00 D RS 1100660 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 28/01/2022 - 07:30 28/01/2022 - 16:00 D RS 1104300 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.