Outage planning results

Last updated: Thu, 18/08/2022 - 10:40
Your current search

Sites: all sites selected

Outages search found 3207 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BOB FDR 272 NNI L 23/09/2022 - 07:00 23/09/2022 - 18:00 D RS 1114561 Approved 07/05/2012 - 15:49
BOB FDR 272 NNI L 22/08/2022 - 07:00 22/08/2022 - 17:00 D RS 1119098 Approved 07/05/2012 - 15:49
BOB FDR 272 NNI L 23/11/2022 - 07:30 23/11/2022 - 16:30 D RS 1097028 Cancelled 07/05/2012 - 15:49
BOB FDR 272 NNI L 26/10/2022 - 08:00 26/10/2022 - 18:30 D RS 1114508 Cancelled 07/05/2012 - 15:49
BOB FDR 212 NNI L 02/11/2022 - 07:00 02/11/2022 - 18:00 D RS 1113106 Approved 07/05/2012 - 15:49
BOB FDR 212 NNI L 01/12/2022 - 06:00 01/12/2022 - 18:00 D RS 1116815 Approved 07/05/2012 - 15:49
OWH RTU 1 NNI G 21/09/2022 - 08:00 21/09/2022 - 16:30 D SCA 1114217 Approved 07/05/2012 - 15:49
OWH RTU 1 NNI G 08/09/2022 - 08:00 08/09/2022 - 16:30 D SCA 1114216 Approved 07/05/2012 - 15:49
OWH RTU 1 NNI G 06/10/2022 - 07:30 06/10/2022 - 17:30 D SCA 1109771 Approved 07/05/2012 - 15:49
BOB RTU 1 NNI G 21/11/2022 - 09:00 21/11/2022 - 15:00 D SCA 1115828 Approved 07/05/2012 - 15:49
BOB RTU 1 NNI G 07/12/2022 - 09:00 07/12/2022 - 15:00 D SCA 1115830 Approved 07/05/2012 - 15:49
BOB RTU 1 NNI G 20/09/2022 - 08:30 20/09/2022 - 16:00 D SCA 1110871 Approved 07/05/2012 - 15:49
BOB RTU 1 NNI G 04/10/2022 - 08:30 04/10/2022 - 16:00 D SCA 1110876 Approved 07/05/2012 - 15:49
BOB RTU 1 NNI G 04/10/2022 - 08:30 04/10/2022 - 16:00 D SCA 1115978 Cancelled 07/05/2012 - 15:49
BOB RTU 1 NNI G 20/10/2022 - 08:00 20/10/2022 - 18:00 D RS 1114505 Approved 07/05/2012 - 15:49
BOB RTU 1 NNI G 13/10/2022 - 08:00 13/10/2022 - 18:00 D RS 1114497 Approved 07/05/2012 - 15:49
BOB RTU 1 NNI G 27/09/2022 - 08:00 27/09/2022 - 18:00 D RS 1114495 Approved 07/05/2012 - 15:49
BOB RTU 1 NNI G 13/09/2022 - 07:00 13/09/2022 - 18:00 D RS 1114462 Approved 07/05/2012 - 15:49
OTA 220CBF NNI G 21/11/2022 - 08:30 21/11/2022 - 18:30 D RS 1117752 Approved 07/05/2012 - 15:49
HAM RTU 1 NNI G 07/09/2022 - 09:00 07/09/2022 - 15:00 D SCA 1115835 Approved 07/05/2012 - 15:49
HEP RTU 1 NNI G 30/03/2023 - 08:00 30/03/2023 - 16:00 D SCA 1117252 Approved 07/05/2012 - 15:49
HEP RTU 1 NNI G 01/02/2023 - 08:00 01/02/2023 - 16:00 D SCA 1117250 Approved 07/05/2012 - 15:49
HEP RTU 1 NNI G 09/03/2023 - 08:00 09/03/2023 - 16:00 D SCA 1117251 Approved 07/05/2012 - 15:49
HEP RTU 1 NNI G 20/04/2023 - 08:00 20/04/2023 - 16:00 D SCA 1117253 Approved 07/05/2012 - 15:49
MNG 110BZ A NNI G 26/06/2023 - 07:30 27/06/2023 - 18:30 D RS 1113276 Approved 07/05/2012 - 15:50
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.