Outage planning results

Last updated: Mon, 20/09/2021 - 16:40
Your current search

Sites: all sites selected

Outages search found 3907 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
WHU FDR 2232 NNI L 24/09/2021 - 06:30 24/09/2021 - 16:00 D RS 1109005 Approved 14/02/2020 - 14:21
BOB HAM 2 NNI G 19/02/2022 - 06:30 20/02/2022 - 19:30 D OPE 1102310 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 11/12/2021 - 07:00 13/12/2021 - 18:00 D OPE 1102266 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 22/02/2022 - 07:30 25/02/2022 - 18:30 D OPE 1101036 Cancelled 07/05/2012 - 15:49
KPO TMU 1 PROT2 NNI G 05/10/2021 - 14:00 05/10/2021 - 18:00 D RS 1106895 Approved 12/07/2021 - 14:29
ARI HTI 1 PROT2 NNI G 08/10/2021 - 10:00 08/10/2021 - 14:00 D RS 1106894 Approved 12/07/2021 - 14:33
KAW MAT 2 PROT2 NNI G 06/10/2021 - 14:00 06/10/2021 - 18:00 D RS 1106475 Approved 07/05/2012 - 15:50
OTA TIE 4 NNI G 07/12/2021 - 07:00 07/12/2021 - 20:00 D RS 1107048 Approved 07/05/2012 - 15:50
HAM C 2 NNI G 30/10/2021 - 07:30 30/10/2021 - 18:30 D RS 1107610 Approved 21/01/2020 - 14:36
KOE MPE 1 PROT2 NNI G 26/10/2021 - 10:00 26/10/2021 - 14:00 D RS 1106619 Approved 13/08/2020 - 16:21
KOE MPE 1 PROT2 NNI G 27/10/2021 - 10:00 27/10/2021 - 14:00 D RS 1106621 Approved 13/08/2020 - 16:21
KOE MPE 2 PROT2 NNI G 26/10/2021 - 14:00 26/10/2021 - 18:00 D RS 1106620 Approved 13/08/2020 - 16:21
KOE MPE 2 PROT2 NNI G 27/10/2021 - 14:00 27/10/2021 - 18:00 D RS 1106622 Approved 13/08/2020 - 16:21
MTI CB 98 NNI G 09/10/2021 - 07:00 09/10/2021 - 14:00 D RS 1108620 Cancelled 01/09/2020 - 11:10
OTA 220BZ 2 NNI G 14/12/2021 - 07:00 14/12/2021 - 18:00 D RS 1108983 Approved 07/05/2012 - 15:50
OTA C 30 NNI G 11/11/2021 - 08:00 11/11/2021 - 16:00 D RS 1107831 Approved 07/05/2012 - 15:50
BRB MDN 1 NNI G 16/03/2022 - 07:30 17/03/2022 - 18:30 D RS 1101166 Approved 07/05/2012 - 15:49
CBG T4 NNI G 03/05/2022 - 07:30 05/05/2022 - 18:30 D RS 1101339 Approved 07/05/2012 - 15:49
CBG T4 NNI G 19/10/2021 - 07:00 19/10/2021 - 17:00 D RS 1102807 Approved 07/05/2012 - 15:49
EDG KAW 2 NNI G 12/01/2022 - 07:30 12/01/2022 - 18:30 D RS 1100804 Approved 07/05/2012 - 15:49
EDG KAW 3 NNI G 03/11/2021 - 07:30 03/11/2021 - 17:30 D RS 1106157 Approved 07/05/2012 - 15:49
OHW OTA 1 NNI G 24/01/2022 - 07:00 24/01/2022 - 18:30 D RS 1106790 Approved 07/05/2012 - 15:50
EDG T5 NNI G 27/01/2022 - 08:00 27/01/2022 - 16:00 D RS 1106429 Approved 07/05/2012 - 15:49
MDN T6 NNI G 14/03/2022 - 07:30 17/03/2022 - 18:30 D RS 1101147 Approved 07/05/2012 - 15:50
GLN T5 NNI G 08/10/2021 - 17:30 08/10/2021 - 18:00 D PSO 1108985 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.