Outage planning results

Last updated: Fri, 18/09/2020 - 19:40
Your current search

Sites: all sites selected

Outages search found 4079 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
TUI RTU 1 SNI G 22/02/2021 - 07:00 22/02/2021 - 17:00 D RS 1082330 Approved 07/05/2012 - 15:52
TUI RTU 1 SNI G 23/02/2021 - 07:00 23/02/2021 - 17:00 D RS 1082332 Approved 07/05/2012 - 15:52
TUI 110BZ SNI G 23/02/2021 - 07:00 23/02/2021 - 17:00 D RS 1082333 Approved 07/05/2012 - 15:53
TUI 110CBF SNI G 23/02/2021 - 07:00 23/02/2021 - 17:00 D RS 1082334 Approved 07/05/2012 - 15:53
MHO T4 SNI G 30/11/2020 - 07:00 09/12/2020 - 17:00 C RS 1082446 Approved 07/05/2012 - 15:52
BPE MHO 2 SNI G 30/11/2020 - 07:00 09/12/2020 - 17:00 C RS 1082448 Approved 07/05/2012 - 15:52
MHO T3 SNI G 13/01/2021 - 07:00 22/01/2021 - 17:00 C RS 1082449 Approved 07/05/2012 - 15:52
BPE MHO 1 SNI G 13/01/2021 - 07:00 22/01/2021 - 17:00 C RS 1082450 Approved 07/05/2012 - 15:52
MHO T4 SNI G 15/03/2021 - 07:00 19/03/2021 - 17:00 C RS 1082523 Approved 07/05/2012 - 15:52
BPE MHO 2 SNI G 15/03/2021 - 07:00 19/03/2021 - 17:00 C RS 1082524 Approved 07/05/2012 - 15:52
MHO T3 SNI G 22/03/2021 - 07:00 26/03/2021 - 17:00 D RS 1082525 Approved 07/05/2012 - 15:52
BPE MHO 1 SNI G 22/03/2021 - 07:00 26/03/2021 - 17:00 D RS 1082526 Approved 07/05/2012 - 15:52
MHO T4 SNI G 29/03/2021 - 07:00 01/04/2021 - 17:00 D RS 1082527 Approved 07/05/2012 - 15:52
BPE MHO 2 SNI G 29/03/2021 - 07:00 01/04/2021 - 17:00 D RS 1082528 Approved 07/05/2012 - 15:52
MHO T3 SNI G 08/03/2021 - 07:00 12/03/2021 - 17:00 C RS 1082533 Approved 07/05/2012 - 15:52
BPE MHO 1 SNI G 08/03/2021 - 07:00 12/03/2021 - 17:00 C RS 1082534 Approved 07/05/2012 - 15:52
RPO WRK 1 SNI G 21/10/2020 - 08:00 22/10/2020 - 17:00 C RS 1082537 Cancelled 07/05/2012 - 15:52
RPO TNG 1 SNI G 27/10/2020 - 08:00 28/10/2020 - 17:00 C RS 1082538 Cancelled 07/05/2012 - 15:52
RPO 526 564 667 SNI G 30/11/2020 - 07:30 30/11/2020 - 18:00 D RS 1082539 Approved 07/05/2012 - 15:52
RPO 567 626 664 SNI G 17/11/2020 - 07:30 17/11/2020 - 18:00 D RS 1082540 Approved 07/05/2012 - 15:53
TUI RTU 1 SNI G 24/02/2021 - 07:00 24/02/2021 - 17:00 D RS 1082556 Approved 07/05/2012 - 15:52
TUI CB 128 SNI G 24/02/2021 - 07:00 24/02/2021 - 12:00 D RS 1082557 Approved 07/05/2012 - 15:52
HAM T4 NNI G 21/10/2020 - 07:30 22/10/2020 - 18:30 C RS 1082691 Approved 07/05/2012 - 15:49
ISL KIK 1 SI G 16/11/2020 - 07:30 21/11/2020 - 18:30 C RS 1082810 Approved 07/05/2012 - 15:51
ISL KIK 1 SI G 07/12/2020 - 07:30 12/12/2020 - 18:30 C RS 1082811 Approved 07/05/2012 - 15:51
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.