Outage planning results

Last updated: Fri, 18/09/2020 - 19:40
Your current search

Sites: all sites selected

Outages search found 4079 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BOB HAM 1 NNI G 09/12/2020 - 20:00 10/12/2020 - 18:30 C OPE 1096223 Approved 07/05/2012 - 15:49
BOB HAM 2 NNI G 09/12/2020 - 20:00 10/12/2020 - 18:30 C OPE 1096224 Approved 07/05/2012 - 15:49
WTU 33BS L SNI L 27/11/2020 - 07:00 02/12/2020 - 18:00 C RS 1096225 Approved 11/02/2014 - 11:32
RDF WTU 1 SNI G 27/11/2020 - 07:00 02/12/2020 - 18:00 C RS 1096226 Approved 07/05/2012 - 15:52
WTU FDR 2212 SNI L 27/11/2020 - 07:00 02/12/2020 - 18:00 C RS 1096227 Approved 29/01/2015 - 10:19
WTU FDR 2232 SNI L 27/11/2020 - 07:00 02/12/2020 - 18:00 C RS 1096228 Approved 11/02/2014 - 11:29
WTU FDR 2242 SNI L 27/11/2020 - 07:00 02/12/2020 - 18:00 C RS 1096229 Approved 11/02/2014 - 11:30
WTU FDR 2252 SNI L 27/11/2020 - 07:00 02/12/2020 - 18:00 C RS 1096230 Approved 11/02/2014 - 11:29
WTU T4 SNI G 27/11/2020 - 07:00 02/12/2020 - 18:00 C RS 1096231 Approved 07/05/2012 - 15:52
WTU CB 2198 SNI L 27/11/2020 - 07:00 02/12/2020 - 18:00 C RS 1096232 Approved 29/01/2015 - 10:21
ROX CB 658 SI G 28/09/2020 - 06:30 28/09/2020 - 17:00 D RS 1096239 Approved 07/05/2012 - 15:51
ROX CB 708 SI G 28/09/2020 - 06:30 28/09/2020 - 17:00 D RS 1096240 Approved 07/05/2012 - 15:51
ROX CB 658 SI G 30/09/2020 - 06:30 01/10/2020 - 17:00 C RS 1096241 Approved 07/05/2012 - 15:51
ROX CB 698 SI G 30/09/2020 - 06:30 01/10/2020 - 17:00 C RS 1096242 Approved 07/05/2012 - 15:51
NAP 184 194 167 SNI G 03/12/2020 - 07:30 04/12/2020 - 18:30 D RS 1096248 Approved 26/10/2012 - 15:05
NAP OKI 2 SNI G 03/12/2020 - 07:30 04/12/2020 - 18:30 D RS 1096249 Approved 17/07/2012 - 16:20
HLY CB 242 NNI G 19/09/2020 - 08:00 26/09/2020 - 18:00 C RS 1096250 Approved 07/05/2012 - 15:49
HLY CB 262 NNI G 19/09/2020 - 08:00 26/09/2020 - 18:00 C RS 1096251 Approved 07/05/2012 - 15:49
HLY CB 542 NNI G 10/10/2020 - 08:00 17/10/2020 - 18:00 C RS 1096252 Approved 07/05/2012 - 15:49
HLY CB 562 NNI G 10/10/2020 - 08:00 17/10/2020 - 18:00 C RS 1096253 Approved 07/05/2012 - 15:49
ISL 220BS CHANGE SI G 22/09/2020 - 07:00 22/09/2020 - 07:30 D PSO 1096254 Approved 07/05/2012 - 15:51
ISL 220BS CHANGE SI G 23/09/2020 - 17:30 23/09/2020 - 18:00 D PSO 1096255 Approved 07/05/2012 - 15:51
ISL 220BS CHANGE SI G 24/09/2020 - 07:00 24/09/2020 - 07:30 D PSO 1096256 Approved 07/05/2012 - 15:51
ISL 220BS CHANGE SI G 25/09/2020 - 18:00 25/09/2020 - 18:30 D PSO 1096257 Approved 07/05/2012 - 15:51
ROX 220CBF SI G 29/10/2020 - 08:30 29/10/2020 - 14:30 D RS 1096258 Approved 07/05/2012 - 15:51
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.