Outage planning results

Last updated: Thu, 14/11/2019 - 08:40
Your current search

Sites: all sites selected

Outages search found 3839 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
GLN CB 2318 NNI G 20/01/2020 - 07:30 21/01/2020 - 18:30 C OPE 1084926 Approved 21/06/2012 - 15:55
GLN CB 2348 NNI G 20/01/2020 - 07:30 21/01/2020 - 18:30 C CLO 1084925 Approved 21/06/2012 - 15:55
EDG T4 NNI G 19/02/2020 - 07:30 19/02/2020 - 18:30 D RS 1084920 Approved 07/05/2012 - 15:49
EDG CB 222 NNI G 19/02/2020 - 07:30 19/02/2020 - 18:30 D RS 1084919 Approved 07/05/2012 - 15:50
EDG 207 217 237 NNI G 19/02/2020 - 07:30 19/02/2020 - 18:30 D RS 1084918 Approved 07/05/2012 - 15:50
MNI FDR 2832 SNI L 29/10/2019 - 13:00 12/12/2019 - 18:00 D RS 1084917 Released 21/08/2019 - 09:51
MAN CB 238 SI G 15/12/2019 - 08:30 15/12/2019 - 16:00 D OPE 1084913 Approved 07/05/2012 - 15:51
MAN CB 238 SI G 03/12/2019 - 08:30 03/12/2019 - 16:00 D OPE 1084912 Approved 07/05/2012 - 15:51
MAN CB 238 SI G 22/11/2019 - 08:30 22/11/2019 - 16:00 D OPE 1084911 Approved 07/05/2012 - 15:51
MAN 220CBF SI G 15/12/2019 - 08:30 15/12/2019 - 16:00 D RS 1084910 Approved 07/05/2012 - 15:51
MAN 220BZ SI G 15/12/2019 - 08:30 15/12/2019 - 16:00 D RS 1084909 Approved 07/05/2012 - 15:51
SBK T1 SI G 07/02/2020 - 07:30 07/02/2020 - 17:30 D RS 1084908 Approved 07/05/2012 - 15:51
KAW T2 NNI G 25/11/2019 - 06:00 25/11/2019 - 21:00 D OPE 1084905 Approved 07/05/2012 - 15:49
EDG TRK 2 NNI G 24/01/2022 - 07:30 28/01/2022 - 18:30 C RS 1084884 Approved 07/05/2012 - 15:49
EDG TRK 2 NNI G 13/12/2021 - 07:30 17/12/2021 - 18:30 C RS 1084883 Approved 07/05/2012 - 15:49
EDG TRK 2 NNI G 08/11/2021 - 07:30 13/11/2021 - 18:30 C RS 1084882 Approved 07/05/2012 - 15:49
EDG TRK 1 NNI G 17/01/2022 - 07:30 21/01/2022 - 18:30 C RS 1084881 Approved 07/05/2012 - 15:49
EDG TRK 1 NNI G 06/12/2021 - 07:30 10/12/2021 - 18:30 C RS 1084880 Approved 07/05/2012 - 15:49
EDG TRK 1 NNI G 01/11/2021 - 07:30 06/11/2021 - 18:30 C RS 1084879 Approved 07/05/2012 - 15:49
MDN MPE 2 NNI G 28/04/2020 - 07:30 01/05/2020 - 18:30 C RS 1084878 Approved 07/05/2012 - 15:49
MDN MPE 1 NNI G 20/04/2020 - 07:30 24/04/2020 - 18:30 C RS 1084877 Approved 07/05/2012 - 15:49
KIN CB 2958 NNI L 15/11/2019 - 18:00 15/11/2019 - 18:30 D PSO 1084876 Approved 18/01/2019 - 16:51
NPL FDR 1092 SNI L 11/12/2019 - 09:00 18/12/2019 - 18:00 C RS 1084875 Approved 07/05/2012 - 15:53
NPL FDR 1042 SNI L 11/12/2019 - 09:00 18/12/2019 - 18:00 C RS 1084874 Approved 07/05/2012 - 15:53
KIN FDR 22 NNI L 11/11/2019 - 14:30 21/01/2020 - 18:30 C RS 1084870 Released 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.