Outage planning results

Last updated: Mon, 26/10/2020 - 19:40
Your current search

Sites: all sites selected

Outages search found 3556 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
HTI 87 97 127 NNI G 27/10/2020 - 06:30 27/10/2020 - 19:30 D RS 1096765 Approved 07/05/2012 - 15:50
MNG FDR 2322 NNI L 28/09/2020 - 07:30 12/02/2021 - 16:00 C RS 1096764 Released 07/05/2012 - 15:49
STK FDR 102 SI G 25/01/2021 - 07:30 27/01/2021 - 18:30 C RS 1096763 Approved 07/05/2012 - 15:51
TKU T22 SNI G 07/11/2020 - 08:00 07/11/2020 - 16:00 D OPE 1096759 Approved 07/05/2012 - 15:52
CST MNI 1 SNI G 22/01/2021 - 07:30 22/01/2021 - 18:30 D RS 1096752 Approved 07/05/2012 - 15:52
EDG 33AFD NNI L 08/03/2021 - 08:00 08/03/2021 - 16:00 D RS 1096749 Approved 27/06/2017 - 13:37
OTA PEN 2 NNI G 09/02/2021 - 07:30 23/03/2021 - 18:30 C RS 1096748 Approved 07/05/2012 - 15:49
WIR T2 NNI G 02/11/2020 - 07:30 04/11/2020 - 18:00 C RS 1096746 Approved 07/05/2012 - 15:49
WKO FDR 2232 NNI L 27/10/2020 - 12:01 31/03/2021 - 18:30 C RS 1096743 Approved 20/08/2020 - 13:52
WKO FDR 2212 NNI L 27/10/2020 - 12:01 31/03/2021 - 18:30 C RS 1096742 Approved 20/08/2020 - 13:49
WKO FDR 2192 NNI L 27/10/2020 - 12:01 31/03/2021 - 18:30 C RS 1096741 Approved 20/08/2020 - 13:49
WKO FDR 2172 NNI L 27/10/2020 - 12:01 31/03/2021 - 18:30 C RS 1096740 Approved 20/08/2020 - 13:48
WKO FDR 2152 NNI L 27/10/2020 - 12:01 31/03/2021 - 18:30 C RS 1096739 Approved 20/08/2020 - 13:35
WHI T2 SNI G 16/12/2020 - 07:30 16/12/2020 - 16:30 D RS 1096738 Approved 07/05/2012 - 15:52
WHI T1 SNI G 15/12/2020 - 07:30 15/12/2020 - 16:30 D RS 1096737 Approved 07/05/2012 - 15:52
RDF WTU GXP TIE SNI G 20/11/2020 - 06:00 25/11/2020 - 19:00 C OTH 1096733 Approved 01/11/2013 - 08:32
HWB CB 2548 SI G 10/02/2021 - 12:30 10/02/2021 - 17:00 D RS 1096727 Approved 16/06/2020 - 11:09
FKN T4 SI G 09/11/2020 - 07:00 20/11/2020 - 18:30 C RS 1096724 Approved 07/05/2012 - 15:51
CML T8 SI G 09/11/2020 - 07:00 20/11/2020 - 18:30 C RS 1096723 Approved 07/05/2012 - 15:52
CML FKN 2 SI G 09/11/2020 - 07:00 20/11/2020 - 18:30 C RS 1096722 Approved 07/05/2012 - 15:51
CYD CML TWZ 2 SI G 09/11/2020 - 07:00 20/11/2020 - 18:30 C RS 1096721 Approved 07/05/2012 - 15:51
CBG T3 NNI G 03/11/2020 - 07:30 05/11/2020 - 18:00 C RS 1096720 Approved 07/05/2012 - 15:49
KPO DIS 251 NNI G 02/11/2020 - 07:30 02/11/2020 - 18:00 D CLO 1096718 Approved 22/11/2019 - 10:04
KPO DIS 261 NNI G 02/11/2020 - 07:30 02/11/2020 - 18:00 D CLO 1096717 Approved 22/11/2019 - 10:05
FHL 97 127 SNI G 03/12/2020 - 07:00 03/12/2020 - 18:00 D RS 1096715 Approved 07/05/2012 - 15:53
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.