Outage planning results

Last updated: Thu, 04/03/2021 - 20:40
Your current search

Sites: all sites selected

Outages search found 2378 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
OTA ROS 2 NNI G 23/05/2021 - 07:00 23/05/2021 - 16:30 D RS 1099624 Approved 07/05/2012 - 15:49
OTA CB 188 NNI G 23/05/2021 - 07:00 23/05/2021 - 16:30 D RS 1099623 Approved 07/05/2012 - 15:50
OTA 127 187 207 NNI G 23/05/2021 - 07:00 23/05/2021 - 16:30 D RS 1099622 Approved 07/05/2012 - 15:49
OTA C 29 NNI G 27/05/2021 - 07:00 28/05/2021 - 18:30 C RS 1099621 Approved 07/05/2012 - 15:49
OHW OTA 1 NNI G 19/05/2021 - 07:00 19/05/2021 - 17:00 D RS 1099620 Approved 07/05/2012 - 15:50
OTA TIE 5 NNI G 02/06/2021 - 07:00 03/06/2021 - 18:00 C RS 1099619 Approved 07/05/2012 - 15:50
OTA CB 538 NNI G 18/05/2021 - 07:00 18/05/2021 - 18:00 D RS 1099617 Approved 07/05/2012 - 15:49
OTA CB 488 NNI G 18/05/2021 - 07:00 18/05/2021 - 18:00 D RS 1099616 Approved 07/05/2012 - 15:50
OTA 487 547 NNI G 18/05/2021 - 07:00 18/05/2021 - 18:00 D RS 1099615 Approved 07/05/2012 - 15:50
OTA CB 528 NNI G 02/06/2021 - 07:00 03/06/2021 - 18:00 C RS 1099614 Approved 07/05/2012 - 15:49
OTA CB 598 NNI G 02/06/2021 - 07:00 03/06/2021 - 18:00 C RS 1099613 Approved 07/05/2012 - 15:49
OTA 527 587 597 NNI G 02/06/2021 - 07:00 03/06/2021 - 18:00 C RS 1099612 Approved 07/05/2012 - 15:50
OTA CB 598 NNI G 31/05/2021 - 07:00 01/06/2021 - 18:00 C RS 1099611 Approved 07/05/2012 - 15:49
OTA CB 538 NNI G 31/05/2021 - 07:00 01/06/2021 - 18:00 C RS 1099610 Approved 07/05/2012 - 15:49
OTA 537 597 587 NNI G 31/05/2021 - 07:00 01/06/2021 - 18:00 C RS 1099609 Approved 07/05/2012 - 15:50
PEN T9 NNI G 17/04/2021 - 07:00 17/04/2021 - 18:00 D RS 1099608 Approved 07/05/2012 - 15:49
PEN CB 772 NNI G 17/04/2021 - 07:00 17/04/2021 - 18:00 D RS 1099607 Approved 03/06/2014 - 14:17
PEN CB 758 NNI G 17/04/2021 - 07:00 17/04/2021 - 18:00 D RS 1099606 Approved 07/05/2012 - 15:50
PEN 757 777 NNI G 17/04/2021 - 07:00 17/04/2021 - 18:00 D RS 1099605 Approved 07/05/2012 - 15:50
MPE 110CBF NNI G 07/03/2021 - 08:00 07/03/2021 - 17:00 D RS 1099523 Approved 18/12/2012 - 13:40
MPE 110BZ NNI G 07/03/2021 - 08:00 07/03/2021 - 17:00 D RS 1099522 Approved 18/12/2012 - 13:40
MPE 110CBF NNI G 05/03/2021 - 08:00 05/03/2021 - 17:00 D RS 1099521 Approved 18/12/2012 - 13:40
MPE 110BZ NNI G 05/03/2021 - 08:00 05/03/2021 - 17:00 D RS 1099520 Approved 18/12/2012 - 13:40
MPE RTU 2 NNI G 24/03/2021 - 08:00 24/03/2021 - 17:00 D SCA 1099507 Approved 07/05/2012 - 15:50
MPE RTU 1 NNI G 24/03/2021 - 08:00 24/03/2021 - 17:00 D SCA 1099506 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.