Outage planning results

Last updated: Fri, 30/10/2020 - 19:40
Your current search

Sites: all sites selected

Outages search found 3531 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
WKM RTU 1 NNI G 10/08/2021 - 08:00 12/08/2021 - 18:30 D RS 1097657 Approved 07/05/2012 - 15:49
OTA WKM 1 NNI G 03/08/2021 - 08:00 05/08/2021 - 18:30 D RS 1097656 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 03/08/2021 - 08:00 05/08/2021 - 18:30 D RS 1097655 Approved 07/05/2012 - 15:49
MTI WKM 2 NNI G 27/07/2021 - 08:00 29/07/2021 - 18:30 D RS 1097654 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 27/07/2021 - 08:00 29/07/2021 - 18:30 D RS 1097653 Approved 07/05/2012 - 15:49
MTI WKM 1 NNI G 20/07/2021 - 08:00 22/07/2021 - 18:30 D RS 1097652 Approved 07/05/2012 - 15:49
BRY ISL 1 PROT1 SI G 09/11/2020 - 06:00 10/11/2020 - 17:30 C OTH 1097651 Cancelled 20/11/2012 - 09:36
WKM RTU 1 NNI G 20/07/2021 - 08:00 22/07/2021 - 18:30 D RS 1097650 Approved 07/05/2012 - 15:49
WKM 220CBF SWYD A NNI G 13/07/2021 - 08:00 15/07/2021 - 18:30 D RS 1097649 Approved 07/05/2012 - 15:49
WKM 220BZ D NNI G 13/07/2021 - 08:00 15/07/2021 - 18:30 D RS 1097648 Approved 07/05/2012 - 15:50
WKM 220BZ C NNI G 13/07/2021 - 08:00 15/07/2021 - 18:30 D RS 1097647 Approved 07/05/2012 - 15:50
WKM 220BZ B NNI G 13/07/2021 - 08:00 15/07/2021 - 18:30 D RS 1097646 Approved 07/05/2012 - 15:49
WKM 220BZ A NNI G 13/07/2021 - 08:00 15/07/2021 - 18:30 D RS 1097645 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 13/07/2021 - 08:00 15/07/2021 - 18:30 D RS 1097644 Approved 07/05/2012 - 15:49
MGM CB 172 SNI G 02/11/2020 - 07:00 05/11/2020 - 17:00 C OPE 1097643 Approved 07/05/2012 - 15:53
BEN 220BS CHANGE SI G 11/11/2020 - 15:00 11/11/2020 - 15:30 D PSO 1097628 Approved 07/05/2012 - 15:52
BEN 220BS CHANGE SI G 11/11/2020 - 07:30 11/11/2020 - 08:00 D PSO 1097627 Approved 07/05/2012 - 15:52
BEN 220BS CHANGE SI G 10/11/2020 - 15:00 10/11/2020 - 15:30 D PSO 1097626 Approved 07/05/2012 - 15:52
BEN 220BS CHANGE SI G 10/11/2020 - 07:30 10/11/2020 - 08:00 D PSO 1097625 Approved 07/05/2012 - 15:52
HAY 110BS CHANGE SNI G 09/11/2020 - 18:00 09/11/2020 - 19:00 D PSO 1097620 Approved 07/05/2012 - 15:53
HAY 110BS CHANGE SNI G 09/11/2020 - 06:30 09/11/2020 - 07:30 D PSO 1097619 Approved 07/05/2012 - 15:53
STK CB 818 SI G 11/11/2020 - 18:00 11/11/2020 - 18:30 D PSO 1097618 Approved 07/05/2012 - 15:51
FHL WTU GXP TIE 2 SNI G 08/12/2020 - 12:00 08/12/2020 - 12:30 D OTH 1097617 Approved 23/07/2020 - 09:18
FHL WTU GXP TIE 2 SNI G 08/12/2020 - 08:00 08/12/2020 - 08:30 D OTH 1097616 Approved 23/07/2020 - 09:18
ROS FDR 62 NNI G 29/10/2020 - 22:00 18/11/2020 - 18:00 C RS 1097615 Released 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.