Outage planning results

Last updated: Tue, 15/06/2021 - 16:40
Your current search

Sites: all sites selected

Outages search found 3563 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
HEP FDR 2342 NNI L 28/10/2021 - 13:00 28/10/2021 - 18:00 D RS 1104984 Approved 17/11/2015 - 10:00
HEP FDR 2352 NNI L 28/10/2021 - 13:00 28/10/2021 - 18:00 D RS 1104985 Approved 17/11/2015 - 10:00
HEP FDR 2362 NNI L 28/10/2021 - 13:00 28/10/2021 - 18:00 D RS 1104986 Approved 17/11/2015 - 10:00
HEP CB 2158 NNI L 27/10/2021 - 13:00 27/10/2021 - 18:00 D RS 1104941 Approved 17/11/2015 - 10:01
HEP CB 2158 NNI L 28/10/2021 - 07:00 28/10/2021 - 12:00 D RS 1104979 Approved 17/11/2015 - 10:01
HEP CB 2278 NNI L 28/10/2021 - 07:00 28/10/2021 - 12:00 D RS 1104980 Approved 17/11/2015 - 10:01
HEP CB 2278 NNI L 28/10/2021 - 13:00 28/10/2021 - 18:00 D RS 1104987 Approved 17/11/2015 - 10:01
HEP 33BS K NNI L 27/10/2021 - 13:00 27/10/2021 - 18:00 D RS 1104935 Approved 17/11/2015 - 10:03
HEP 33BS L NNI L 28/10/2021 - 07:00 28/10/2021 - 12:00 D RS 1104972 Approved 17/11/2015 - 10:03
HEP 33BS M NNI L 28/10/2021 - 13:00 28/10/2021 - 18:00 D RS 1104981 Approved 17/11/2015 - 10:04
PEN 1678 2213 2215 NNI L 14/01/2022 - 07:30 14/01/2022 - 18:30 D RS 1103881 Approved 20/11/2015 - 09:50
WTK CB 1002 SI G 28/06/2021 - 07:30 30/06/2021 - 18:30 C CLO 1104470 Approved 24/11/2015 - 15:25
WTK CB 1002 SI G 16/05/2022 - 07:30 20/05/2022 - 18:30 C CLO 1101377 Approved 24/11/2015 - 15:25
SDN FDR 2292 SI L 14/06/2021 - 08:30 18/06/2021 - 16:30 C RS 1104854 Released 29/01/2016 - 07:54
SDN FDR 2182 SI L 04/10/2021 - 07:00 08/10/2021 - 18:00 C RS 1103917 Approved 29/01/2016 - 07:55
TGA CB 2188 NNI L 22/06/2021 - 08:00 22/06/2021 - 18:00 D RS 1098473 Approved 11/03/2016 - 13:22
TGA CB 2208 NNI L 24/06/2021 - 08:00 25/06/2021 - 18:00 D RS 1098475 Approved 11/03/2016 - 13:23
TGA CB 2348 NNI L 29/06/2021 - 08:00 30/06/2021 - 18:00 D RS 1098485 Approved 11/03/2016 - 13:24
HWA CB 602 SNI G 20/07/2021 - 07:00 20/07/2021 - 18:00 D RS 1104519 Approved 03/05/2016 - 14:27
HWA CB 602 SNI G 31/05/2021 - 07:30 30/06/2021 - 14:00 C RS 1105320 Released 03/05/2016 - 14:27
PEN FDR 2532 NNI L 02/05/2018 - 23:07 15/03/2023 - 18:00 C RS 1066297 Released 09/05/2016 - 10:00
HEN 33BS K NNI L 29/10/2021 - 13:00 29/10/2021 - 18:00 D RS 1104996 Approved 16/06/2016 - 09:52
HEN 33BS M NNI L 29/10/2021 - 07:00 29/10/2021 - 12:00 D RS 1104988 Approved 16/06/2016 - 09:53
HEN FDR 2132 NNI L 09/11/2016 - 18:30 18/12/2021 - 18:30 C RS 1049684 Released 16/06/2016 - 09:53
HEN FDR 2142 NNI L 29/10/2021 - 13:00 29/10/2021 - 18:00 D RS 1105003 Approved 16/06/2016 - 09:53
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.